up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the restoration of, or improvements to, Wheaton parking facilities to address deterioration due to use and age. This is a continuing program of contractual improvements or restorations, with changing priorities depending upon the types of deterioration and corrections required. Corrective measures are required to ensure adequate and proper serviceability over the design life of the facilities and to preserve the County's investment. The scope of this project may vary depending on the results of the studies conducted under Facility Planning: Parking.
project image
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$2.84M Total
Expenditures/Funding
$1.58M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Cost Change

Cost increase is due to the addition of FY31 and FY32 to this Level of Effort project, as well as additional funding in FY27 for legacy parking meter replacement.
anchor

Justification

Staff inspection and condition surveys by County inspectors and consultants indicate that facilities at the Wheaton Parking Lot District (PLD) are in need of rehabilitation and repair work. Not performing this restoration work within the time and scope specified may result in serious structural integrity problems to the subject parking facilities as well as possible public safety hazards.
anchor

Other

Major sub projects within this ongoing effort are as follows: Garage 13 - Gate installation and repairs; Garage 45 - expansion joint repairs near elevator tower; and Lots 14 and 17 - upgrade and install LED lights.
anchor

Fiscal Note

FY26 supplemental in the amount of $34,650 in State aid from the Maryland Energy Administration for LED lighting installation and upgrades.
anchor

Disclosures

Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Facility Planning Parking: Wheaton Parking Lot District
Download & Explore Project Details
Budget Snapshot
$2.84M Total
Expenditures/Funding
$1.58M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP509709
Date Last Modified02/10/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryParking
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision3722820901515151515150
Land55000000000
Site Improvements and Utilities00000000000
Construction245648149014853102352352352352350
Other66000000000
Total Expenditures283977449015753252502502502502500
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Current Revenue: Parking - Wheaton280477445515753252502502502502500
State Aid3503500000000
Total Funding Sources283977449015753252502502502502500
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request325
Year First AppropriationFY97
Appropriation FY 28 Request250
Last FY's Cost Estimate2233
Cumulative Appropriation1264
Expenditure / Encumbrances1072
Unencumbered Balance192
anchor
Download & Explore Project Details