up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Parklawn Entrance Bridge over Rock Creek in Rockville. The existing bridge, built in 1950, is an approximately 42.5' long single span structure with four rolled steel beams and a timber deck supported by concrete cantilever abutments and concrete wingwalls. It provides a 10'-6" wide clear roadway to accommodate both the Rock Creek Trail and a single lane for two-way vehicular traffic on Parklawn Entrance. It provides the only access to a resident property and the Parklawn community garden. The proposed replacement bridge will be a 50' span prestressed concrete adjacent solid slab structure with a concrete overlay. It will carry a single 10' wide vehicular lane for two-way traffic, along with a 2' wide striped buffer zone with a flexible longitudinal separator and a 10' wide shared use path to accommodate pedestrians and cyclists using the Rock Creek Trail. The proposed bridge will be constructed on a new alignment and will require relocation of both Parklawn Entrance and Rock Creek Trail within the vicinity of the bridge. The relocated portions of Parklawn Entrance and Rock Creek Trail will feature a raised profile compared to the existing ground. This new alignment will allow the existing bridge to remain open and accessible to vehicles, pedestrians and cyclists during construction. A temporary trail alignment will be required both east and west of the proposed bridge. The project scope also includes installation of stream restoration structures to provide grade control and stream stabilization at the location of the replacement structure and around the upstream bend. Accelerated bridge construction techniques (ABC) will be utilized to minimize the disruption to the traveling public and local community.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$5.26M Total
Expenditures/Funding
$5.26M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 40 vehicles.
anchor

Estimated Schedule

The design of the project is expected to finish in FY29 within the Bridge Design Project (509132). Construction is scheduled to start in FY30 and be completed in FY31.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the travelling public. The recent Bridge Inspection Report for Bridge No. M-PK17 indicates that steel beams are in deteriorating condition. There are typically sections of up to 3/16" deep painted over pitting on the bottom of the beam web faces. The bolts connecting the bottom flange of the beams to the abutments are typically leaning at both abutments and exhibit up to 75 percent section loss. There are multiple inactive areas of 100 percent section loss in Beams 2 and 3. Several diaphragm connections at mid-span have cracks in welds between diaphragm and beam. The superstructure has been cleaned and painted, and several plating repairs have been installed. These repairs were meant to be temporary and to keep the bridge safe until the replacement design could be completed. In addition, the existing bridge railings do not meet current safety standards and erosion is occurring along the existing stream banks. The bridge is currently posted for a 14,000 lbs. limit for a single-unit truck and a 26,000 lbs. for a combination-unit truck. Implementation of this project would allow the bridge to be restored to full capacity.

The Parklawn Entrance Bridge is owned by the Maryland-National Capital Park & Planning Commission (M-NCPPC). The Bicycle Master Plan designates this segment of Rock Creek Trail - from Avery Rd to Veirs Mill Rd Trail Connector as a Stream Valley Park Trail.
anchor

Fiscal Note

The design costs for this project are covered in the Bridge Design project (CIP 509132). The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal Aid. A design exception for single lane bridge design has been received for Federal Aid funding.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement and Rehabilitation Program, Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, and Bridge Design Project CIP 509132
Download & Explore Project Details
Budget Snapshot
$5.26M Total
Expenditures/Funding
$5.26M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502705
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision104100104100027576600
Land00000000000
Site Improvements and Utilities12000120000586200
Construction40980040980001018308000
Other00000000000
Total Expenditures52590052590001351390800
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid3802003802000941286100
G.O. Bonds1457001457000410104700
Total Funding Sources52590052590001351390800
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0
anchor
Download & Explore Project Details