up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project will provide a permanent stream crossing in the form of a pedestrian bridge to facilitate movement between Auth Lane and Kersey Road. In September of 2020, members of the Kemp Mill community requested a pedestrian bridge to increase safety and to facilitate the use of an existing natural path by any individuals who are unable to ford the stream. Community members currently use the natural path on a section of unimproved public right-of-way as a short cut between Auth Lane and Kersey Road. The path includes an "at grade" stream crossing which is hazardous due to the presence of rocks and steep slopes and cannot be crossed during high stream flow events.
anchor

Phase

Final Design Stage

Status

New
anchor
Budget Snapshot
$0.25M Total
Expenditures/Funding
$0.25M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

This project will be constructed in FY25.
anchor

Justification

The objective of this project is to provide a pedestrian bridge over a stream which bisects an existing natural path currently used by the public. The pedestrian bridge will eliminate hazards typically associated with fording an active stream and will increase pedestrian safety. A feasibility study and associated engineering work for this project was initiated in Fiscal Year 2023 to determine the project scope, cost, as well as potential environmental and property impacts. The feasibility study concluded that construction of a pedestrian bridge to facilitate pedestrian movement between Auth Lane and Kersey Road is feasible.
anchor

Other

Feasibility study and engineering design for this project was completed in FY23 and FY24 under CIP No. 502303 (Transportation Feasibility Studies).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Montgomery County Department of Environmental Protection, Montgomery County Department of Permitting Services, Maryland Department of the Environment, Maryland Department of Natural Resources, United States Army Corps of Engineers
Download & Explore
Budget Snapshot
$0.25M Total
Expenditures/Funding
$0.25M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502505
Date Last Modified01/07/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision50005050000000
Land00000000000
Site Improvements and Utilities00000000000
Construction20000200200000000
Other00000000000
Total Expenditures25000250250000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds25000250250000000
Total Funding Sources25000250250000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Maintenance25-55555
NET IMPACT25-55555
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request250
Year First AppropriationFY25
Appropriation FY 26 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0