This project provides for the design and construction of a roadway extension of North High Street to Morningwood Drive in Olney. The project also provides a continuous 6-foot sidewalk on the south side of North High Street and ADA-compliant pedestrian access from Morningwood Drive. Additionally, about 500-feet of traffic calming curb bump-outs will be built along Morningwood Drive south of North High Street.
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$3.77M Total
Expenditures/Funding
$1.81M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design began in FY23 and will be completed in FY26. Land acquisition will begin in FY26 and construction will begin and be completed in FY27.
anchor

Cost Change

Project cost increase due to WSSC Water relocation design and rising construction costs.
anchor

Justification

The purpose of the project is to improve safety and enhance connectivity within the Olney town center vicinity. This project is supported by the Greater Olney Civic Association and will provide vehicular, pedestrian, and bicycle access to North High Street from Morningwood Drive instead of Georgia Avenue (MD 97). This project also supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Greater Olney Civic Association, Olney Town Center Advisory Committee
Download & Explore Project Details
Budget Snapshot
$3.77M Total
Expenditures/Funding
$1.81M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502310
Date Last Modified01/09/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision1274360565349349000000
Land4230317106106000000
Site Improvements and Utilities110011000000000
Construction1960160513541354000000
Other00000000000
Total Expenditures3767361159718091809000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds3617361159716591659000000
Intergovernmental15000150150000000
Total Funding Sources3767361159718091809000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance25-55555
NET IMPACT25-55555
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request1348
Year First AppropriationFY23
Appropriation FY 28 Request0
Last FY's Cost Estimate2419
Cumulative Appropriation2419
Expenditure / Encumbrances706
Unencumbered Balance1713