up
Budget Year / Version:  
anchor
anchor
anchor

Description

The project provides for a cost share with the Maryland Department of Transportation State Highway Administration (MDOT SHA) for the final design and construction of a ten foot wide shared use path on the north side of MD 108 from Dr. Bird Road to Norwood Road. The project is approximately .86 of a mile and will complete missing segments of existing shared use paths along the MD 108 corridor. Where feasible, drainage improvements are included in the scope of the project.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$0.3M Total
Expenditures/Funding
$0.1M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

MDOT SHA started Design in FY 23. Construction, also by MDOT SHA, is anticipated in FY 25 and 26
anchor

Cost Change

Cost increase is due to the addition of land costs.
anchor

Justification

Constructing these segments will help close a significant gap in Montgomery County's active transportation system. As a critical component of multi-modal infrastructure, these sidewalks and shared use paths will connect residents and visitors to destinations along the corridor such as the: Olney Theatre, Sherwood Elementary School and High School, area restaurants and retail, and transit in Sandy Spring. This project is part of the Heritage Triangle Trail, which will provide for a safe walkable and bikeable shared use path network to the existing cultural resources in the Sandy Spring/Ashton and Olney area. This project will comply with the 2018 Approved and Adopted Montgomery County Bicycle Master Plan, the Sandy Spring and Ashton Master Plans and the Vision Zero 2030 Plan goals.
anchor

Other

The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries within the County's roadways to zero by 2030 and to provide a safe, low stress and connected bicycle network.
anchor

Fiscal Note

The County is providing $200,000 as part of its contribution to the final design to be completed by the Maryland Department of Transportation State Highway Administration through the Bicycle Retrofit Program. Additional County funding will be needed to provide a 25 percent match of the total construction cost and all of the land acquisition costs. Additional funding amounts will be determined at the conclusion of design.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland DOT State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Montgomery County Department of Environmental Protection, Utility Companies
Download & Explore
Budget Snapshot
$0.3M Total
Expenditures/Funding
$0.1M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502306
Date Last Modified10/30/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaPatuxent Watershed Conservation Area
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision200020000000000
Land10000100100000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures3000200100100000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds3000200100100000000
Total Funding Sources3000200100100000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request100
Year First AppropriationFY23
Appropriation FY 26 Request0
Last FY's Cost Estimate200
Cumulative Appropriation200
Expenditure / Encumbrances0
Unencumbered Balance200