up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Mouth of Monocacy Road Bridge over Little Monocacy River. The existing bridge, built in 1971, is a 49' long single-span structure with steel beams and corrugated metal deck. The existing clear roadway width is 14'-9" with one lane on the bridge carrying two-way traffic. The proposed replacement bridge includes a single-span steel beam structure carrying a 14'-9" roadway. The proposed structure will utilize drilled shaft-supported abutments behind the existing cantilever abutments to support a slightly longer steel superstructure. The project includes approach roadway work at each end of the bridge to tie into the existing roadway. The bridge and road will be closed to traffic during construction. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$3.16M Total
Expenditures/Funding
$3.06M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The Average Daily Traffic (ADT) is approximately 75 vehicles and the roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

The design and land acquisition are expected to be completed in FY27. Construction is scheduled to begin in FY28 and complete in FY29.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the public. Mouth of Monocacy Road Bridge M-0043 is defined as structurally deficient due to the condition of the superstructure. Recent inspections revealed that the steel beams and bearings are in poor condition. The top and bottom flange of the exterior beam have severe pitting with up to 33 percent section loss over most of the length. The bottom flanges of exterior beams have up to 66 percent section loss at both abutments up to 1'-0" from the bearing locations. The bottom flanges and the full-height of the web at each end of the interior beams have severe section loss with pitting up to 2.5" in diameter at the beam ends. The bearings have over 50 percent section loss to the bearing plates. The bridge has posted load limits of 56,000 Gross Vehicle Weight (GVW) and 66,000 Gross Combined Weight (GCW). Implementation of this project would allow the bridge to be restored to full capacity. The 1996 approved and adopted Rustic Roads Functional Master Plan designates Mouth of Monocacy Road as Exceptional Rustic Road (E-6) from Mt. Ephraim Road to the bridge over Little Monocacy River with minimum right-of-way width of 80'. The bridge provides the only means of access to about ten homes.
anchor

Fiscal Note

The design costs for this project are covered in the Bridge Design project (No. 509132). The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal Aid.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement and Rehabilitation Program, Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Rustic Road Advisory Committee, CSX Transportation, Utilities, and Bridge Design Project (CIP 509132).
Download & Explore Project Details
Budget Snapshot
$3.16M Total
Expenditures/Funding
$3.06M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP502103
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaLittle Monacacy Basin Dickerson-Barnesville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision7700077001006700000
Land100010000000000
Site Improvements and Utilities00000000000
Construction2290002290050017900000
Other00000000000
Total Expenditures316001003060060024600000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid3060003060060024600000
G.O. Bonds100010000000000
Total Funding Sources316001003060060024600000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY25
Appropriation FY 28 Request3060
Last FY's Cost Estimate3160
Cumulative Appropriation100
Expenditure / Encumbrances0
Unencumbered Balance100
anchor
Download & Explore Project Details