up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Glen Road Bridge over Sandy Branch. The existing bridge, built in 1930 and repaired in 1992, is a 12-foot-long single-span concrete slab structure with concrete abutments and wingwalls. The bridge provides a 21'-7" wide clear roadway. The proposed replacement bridge includes a two-cell 10'x10' box culvert carrying an 18'-0" roadway and a 2'-0" shoulder on each side. The project includes approach roadway work at each end of the bridge to tie into the existing roadway. The project also includes 360 feet of stream restoration. The area of stream restoration on the upstream side is increased, thus increasing the limit of disturbance of the project. The bridge and road will be closed to traffic during construction. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$4.86M Total
Expenditures/Funding
$4.29M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 3,846.
anchor

Estimated Schedule

Design is expected to be completed in the summer of 2024. Construction is scheduled to begin in the summer of 2025 and complete in the fall of 2025. The bridge will be closed to traffic during the school summer break of 2025.
anchor

Cost Change

Cost increases due to increased stream restoration on the upstream side of the bridge requested by The Glenstone Foundation, plus inflation, and escalation of bid prices.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the travelling public. The 2015 bridge inspection report for Bridge No. M-0148X01 indicates that there are concrete spalls on the north fascia, and at the northeast corner of the soffit. There is a 6" diameter x 2" deep spall with exposed reinforcement adjacent to the west abutment. There is a 3'-0" long hairline crack with minor spalling up to 2" high and delamination in the northwest wing wall interface with the north fascia. There is a 2.5" deep spall and full height vertical fracture in the southeast wing wall interface with the east abutment. The bridge is currently posted for a 26,000 lbs. limit for a single-unit truck and a 26,000 lbs. limit for a combination-unit truck. Implementation of this project would allow the bridge to be restored to full capacity. The 2002 Potomac Subregion Master Plan designates Glen Road as Rustic Road (R-2) from Query Mill Rd to Piney Meetinghouse Rd with two travel lanes and minimum right-of-way width 70 of feet.
anchor

Other

The design costs for this project are partially covered in the "Bridge Design" project (CIP No. 509132).
anchor

Fiscal Note

Since the existing bridge is less than 20 feet long, construction and construction management costs for this project are not eligible for Federal Aid. Stream restoration work in this project is partially funded with Water Quality Protection Fund revenues.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, and Bridge Design Project CIP 509132.
Download & Explore
Budget Snapshot
$4.86M Total
Expenditures/Funding
$4.29M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502102
Date Last Modified03/09/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaTravilah and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision111319130961321739600000
Land1580689090000000
Site Improvements and Utilities9850098548550000000
Construction2604002604500210400000
Other00000000000
Total Expenditures486019137742921292300000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Current Revenue: Water Quality Protection35000350035000000
G.O. Bonds451019137739421292265000000
Total Funding Sources486019137742921292300000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request275
Year First AppropriationFY21
Appropriation FY 26 Request0
Last FY's Cost Estimate4585
Cumulative Appropriation4585
Expenditure / Encumbrances586
Unencumbered Balance3999