This project provides for the renovation, upgrade, expansion, and enhancement of the outdoor firing range and its support facilities. The Montgomery County Department of Police (MCPD) outdoor firing range and its support facilities is a multipurpose tactical training facility that serves as the primary MCPD training area for open-air environments and scenarios. The primary purpose of the outdoor firing range and its support facilities is to train MCPD Police personnel along with other municipalities and agencies in the area. The facility is strategically important and heavily used because the site is large and isolated from the County's residential and commercial development within the Agricultural Reserve. The facility provides the rare opportunity to provide realistic advanced training that is increasingly difficult to obtain and provides beneficial joint training with multiple area agencies including: Montgomery County Sheriff's Office, Montgomery County Department of Correction and Rehabilitation, Gaithersburg City Police, Rockville City Police, and other law enforcement agencies.

The project scope intends to: increase and refurbish the earthen protection berms on both sides and at the end of the rifle and pistol ranges; increase the number of lanes in the rifle range with an appropriate target system; increase the distance of the pistol range lanes with an appropriate target system; provide an open air pavilion for weapons cleaning; and provide a new explosive bunker.

project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$9M Total
Expenditures/Funding
$0.3M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Development of Program of Requirements to occur in FY27.
anchor

Cost Change

Cost increases reflect project escalation.
anchor

Justification

The project scope reflects needs based on current and projected Police staff growth, the increasing demands and challenges of meeting certification and best practice training requirements, and the need for improved training.
anchor

Other

The Program of Requirements should ensure the new project will reflect updated standards for: training for the appropriate and accurate use of force; training for the appropriate and accurate use of de-escalation; training that enhances improved decision-making under stress; scenario-based training and readiness; site safety, including health and occupational safety requirements for officers and others who use the facility; and adequate, safe, and secure ammunition storage and firearms cleaning and storage.
anchor

Fiscal Note

During the course of the project development of the design and construction, MCPD will pursue potential grant and partner funding to augment and potentially reduce the overall project cost to the County. In FY27, $300,000 in funding is programmed to complete a new Program of Requirements for the Outdoor Firearms Training Center.
anchor

Coordination

Department of General Services, Department of Technology and Enterprise Business Solutions, and Department of Police.
Download & Explore Project Details
Budget Snapshot
$9M Total
Expenditures/Funding
$0.3M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP472101
Date Last Modified12/30/25
Administering AgencyGeneral Services
CategoryPublic Safety
SubCategoryPolice
Planning AreaPoolesville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision252100300300000002221
Land00000000000
Site Improvements and Utilities55810000000005581
Construction479000000000479
Other416000000000416
Total Expenditures899700300300000008697
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Current Revenue: General30000300300000000
G.O. Bonds86970000000008697
Total Funding Sources899700300300000008697
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request300
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate5920
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0