Description

This project provides for a new Fire and Rescue Station in the Clarksburg area and the purchase of a tanker truck. The new station will be constructed in accordance with square footage specifications of the prototype Program of Requirements (POR) for a Class I Fire Station. A Class I Fire Station is approximately 22,600 gross square feet and includes apparatus bays, personal protective equipment storage, dormitory and support space, living and dining areas, administrative offices, and a meeting/training room. This station is two stories and an addition includes offices for a Battalion Chief, a Police satellite facility, additional space for the Upcounty Regional Services Center, and has a total of 24,200 gross square feet. On-site parking will be provided.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$30.77M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Construction began in fall of 2021 and will be completed in winter of 2024.
anchor

Justification

A new station will be necessary in this area due to the present and projected population density for the Clarksburg area. The Clarksburg population was estimated at 18,709 in 2015, and is projected to increase to almost 40,000 by 2025. The Clarksburg Town Center is envisioned to include a mix of housing, commercial, retail, recreation, and civic uses, with the Clarksburg Historic District as the focal point. Residential areas include the Newcut Road neighborhood, the Cabin Branch neighborhood, the Ten Mile Creek area, the Ridge Road transition area, the Brink Road transition area, as well as projected residential development in the Transit Corridor District and the Gateway Center. This project was recommended in the Fire, Rescue, Emergency Medical Services and Community Risk Reduction Master Plan approved by the County Council in October 2005 and the Montgomery County Fire and Rescue Service Station Location and Resource Allocation Work Group, Phase I Report, "Need for Upcounty Fire-Rescue Resource Enhancements, October 14, 1999." Development of this facility will help Montgomery County meet the National Fire Protection Association (NFPA) 1710 Guidelines.
anchor

Other

This project includes the cost to provide both Phase I and Phase II of the Historic Clarksburg Sewer project.
anchor

Fiscal Note

Intergovernmental funds totaling $2,533,000 in FY18 and FY19 reflect WSSC Water contributions toward the cost of the Phase I and Phase II of the Historic Clarksburg Sewer project. Debt service for this project will be financed with Consolidated Fire Tax District Funds. Land cost was transferred from ALARF. Funding switch between GO bonds and GO bond Premium in FY24 for $4.23 million. FY25 transfer of $1.3 million to the Public Safety Communications Center, Phase II, Electrical Distribution and HVAC Upgrade (P472102).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Montgomery County Fire and Rescue Service, Department of Police, Upcounty Regional Services Center, Department of General Services, Department of Permitting Services, Department of Technology and Enterprise Business Solutions, Maryland-National Capital Park and Planning Commission, State Highway Administration, Washington Gas, WSSC Water. Special Capital Projects Legislation [Bill No. 07-06] was adopted by County Council May 25, 2006, and Expedited Bill No. 22-18 was adopted by County Council on June 19, 2018.
Budget Snapshot
$30.77M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP450300
Date Last Modified12/29/25
Administering AgencyGeneral Services
CategoryPublic Safety
SubCategoryFire/Rescue Service
Planning AreaClarksburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision76487648000000000
Land20382038000000000
Site Improvements and Utilities21572157000000000
Construction1763617636000000000
Other128912731600000000
Total Expenditures30768307521600000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bond Premium42304230000000000
G.O. Bonds24005239891600000000
Intergovernmental25332533000000000
Total Funding Sources30768307521600000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance588989898989898
Energy384646464646464
NET IMPACT972162162162162162162
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY03
Appropriation FY 28 Request0
Last FY's Cost Estimate30768
Cumulative Appropriation30768
Expenditure / Encumbrances30768
Unencumbered Balance0