Description

Based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. This project will address aging infrastructure and meet programmatic objectives. Due to fiscal constraints, the County Council, in the adopted FY2023-2028 CIP, delayed this project by two years. As part of the adopted FY2023-2028 CIP, an additional $22.926 million from the County Executive's Built To Learn Act PDF was included in this project. Due to fiscal constraints, as part of the County Council's approved FY2025-2030 CIP, planning and construction expenditures were shifted to the outyears of the CIP with a "to be determined" completion date. An appropriation for planning funds will be considered in a future CIP.

project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$63.19M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$63.19M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP652116
Date Last Modified05/06/24
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision31570000000003157
Land00000000000
Site Improvements and Utilities53820000000005382
Construction5234700000000052347
Other23000000000002300
Total Expenditures6318600000000063186
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds4618600000000046186
State Aid1700000000000017000
Total Funding Sources6318600000000063186
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First Appropriation
Appropriation FY 26 Request0
Last FY's Cost Estimate63186
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0