up
Budget Year / Version:  
anchor
anchor
anchor

Description

Projections indicate that enrollment will exceed capacity by the end of the six-year planning period. In addition, based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. An FY 2021 appropriation was approved for the architectural planning and design for this project. An FY 2022 appropriation was approved for construction funds. An FY 2022 supplemental appropriation and transfer of funds of $12.873 million for this project was approved for construction cost increases. An FY 2023 appropriation was approved to complete this project. As part of the adopted FY2023-2028 CIP, an additional $37.298 million from the County Executive's Built To Learn Act PDF was included in this project. An FY 2024 appropriation and amendment to the FY2023-2028 CIP was approved for additional funds due to the impact of construction costs as a result of the Covid-19 pandemic. This Major Capital Project is scheduled to be completed August 2024.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$129.48M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid approved from the County's allocation of the Built To Learn Act school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$129.48M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP652113
Date Last Modified12/19/25
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaPoolesville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision51175117000000000
Land00000000000
Site Improvements and Utilities1442214422000000000
Construction104726891931553300000000
Other52193189203000000000
Total Expenditures1294841119211756300000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds40590230301756000000000
Recordation Tax3883738834300000000
State Aid4992849928000000000
Utilization Premium Payment129129000000000
Total Funding Sources1294841119211756300000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY21
Appropriation FY 28 Request0
Last FY's Cost Estimate129484
Cumulative Appropriation129484
Expenditure / Encumbrances0
Unencumbered Balance129484