up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project will increase the stormwater treatment area for overflow parking areas at The Crossvines. The additional parking was added after construction was complete, and the increased impermeable surface requires additional stormwater treatment.
anchor

Phase

Planning Stage

Status

New
anchor
Budget Snapshot
$0.2M Total
Expenditures/Funding
$0.2M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

The Authority is created to construct, improve, equip, furnish, maintain, acquire, operate, and finance projects to be devoted wholly or partially for public uses, good or general welfare. This project supports the long term sustainability of the County's golf course system currently operated by the Revenue Authority.
Download & Explore Project Details
Budget Snapshot
$0.2M Total
Expenditures/Funding
$0.2M 6 Year Total
Expenditures/Funding
anchor
Project NumberP392703
Date Last Modified01/07/26
Administering AgencyRevenue Authority
CategoryRevenue Authority
SubCategoryMiscellaneous Projects (Revenue Authority)
Planning AreaPoolesville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities20000200200000000
Construction00000000000
Other00000000000
Total Expenditures20000200200000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Revenue Authority20000200200000000
Total Funding Sources20000200200000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0
anchor
Download & Explore Project Details