up
Budget Year / Version:  
anchor
anchor
anchor

Description

The Rock Creek Trail Pedestrian Bridge spans Veirs Mill Road at Aspen Hill Road in Rockville. It connects portions of the 15-mile hard surface trail from Beach Drive at the District of Columbia line to Lake Needwood in Rock Creek Regional Park. The trail currently crosses Veirs Mill Road at grade at its signalized intersection with Aspen Hill Road. To the north of Veirs Mill Road, the trail is on sidewalk for approximately 0.2 miles traversing Aspen Hill Road, Adrian Street, Baltic Avenue, and finally the access drive to Aspen Hill Local Park before continuing northward as a trail. The proposed pedestrian bridge will provide a grade separated crossing for the Rock Creek Hiker-Biker Trail and eliminates the use of the residential section. It will also provide the opportunity for local residents of the Aspen Hill community to cross Veirs Mill Road on the bridge to access bus transit or other destinations without crossing at grade the busy intersection of Veirs Mill Road and Aspen Hill Road.
project image
anchor

Phase

Ongoing

Status

Pending Closeout
anchor
Budget Snapshot
$7.94M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Pending Closeout.
anchor

Justification

February 13, 2001, Resolution 14-773. The Planning Board approved the facility plan on September 11, 2003. Aspen Hill Master Plan, approved 1994. Countywide Plan of Trails, approved 1998.
anchor

Fiscal Note

In FY10, $269,000 GO Bonds transferred in from Pope Farm Nursery, PDF #058707. In FY10, M-NCPPC received $261,000 in developer contributions for Policy Area Mobility Review (PAMR) mitigation. This contribution will off-set $261,000 in POS funds. In FY10, $175,000 (General Obligation Bonds) was transferred in from Pope Farm Nursery Utilities Upgrade, PDF# 058707. FY09 amendment and supplemental appropriation: $1,589,000 in Transportation Enhancement Program funds.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. M-NCPPC asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Trails: Hard Surface Design and Construction PDF 768673, Montgomery County Department of Transportation, State of Maryland Department of Transportation
Download & Explore
Budget Snapshot
$7.94M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP048703
Date Last Modified11/21/23
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaAspen Hill and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision7706888200000000
Land00000000000
Site Improvements and Utilities7173640676700000000
Construction00000000000
Other00000000000
Total Expenditures7943709484900000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Contributions261261000000000
G.O. Bonds3207235884900000000
Program Open Space13701370000000000
TEA-2123682368000000000
Transportation Enhancement Program737737000000000
Total Funding Sources7943709484900000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY05
Appropriation FY 26 Request0
Last FY's Cost Estimate7943
Cumulative Appropriation7943
Expenditure / Encumbrances7172
Unencumbered Balance771