Description

This project provides for the remediation of low-level environmental contamination at the Gude Landfill. The Maryland Department of the Environment (MDE) approved an Assessment of Corrective Measures (ACM) report for Gude Landfill in July 2016 which specifically outlines the approved Corrective Measure Alternative (CMA) for this remediation project. The MDE approved CMA will include toupee capping (regrading and capping the top of the landfill and selected slope areas with a synthetic liner and two feet of soil) and increased gas collection through the installation of additional gas extraction wells. These remediation measures will reduce infiltration of rainwater into the landfill resulting in the generation of less leachate, fewer leachate seeps, and better control of landfill gas migration.
project image
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$61.75M Total
Expenditures/Funding
$58.93M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

The Gude Landfill Remediation project construction will begin in FY22 and is scheduled to be completed in FY27.
anchor

Cost Change

Costs increased due to updated estimates from a Maryland Department of the Environment-approved scope. A delay in construction is also reflected as DEP considers phasing to reduce costs. New 60% design documents based on the phasing and an updated cost estimate are expected in early 2020. The scope, design, and cost are subject to final MDE review, and continued cost refinements are expected.
anchor

Justification

The County and MDE entered a consent order in May 2013 which outlined requirements for assessing low-level groundwater contamination, gas migration, and other problems at the Gude Landfill. The Consent Order included provisions requiring a Work Plan and schedule to be established for assessing potential risks to human health and the environment, and development of an ACM report and implementation schedule. After consultation with industry experts, community groups, MDE, and County government leadership, the Department of Environmental Protection's (DEP) initial proposal to MDE in 2014 addressed the low-level groundwater contamination at the site with installation of bioremediation wells on the property. MDE's assessment of this bioremediation corrective measure in April 2015 determined that additional corrective measures would need to be included in the bioremediation approach to address all of MDE's requirements. A revised ACM report was submitted to MDE in April 2016 addressing all MDE's comments and selecting corrective measures consisting of a toupee cap, additional landfill gas collection, and stormwater drainage improvements. The County has been mandated to perform work outlined in the consent order. Moving forward with the remediation of Gude Landfill, as required by MDE, will also address concerns raised by the adjacent community and allow planning for future reuses of the property.
anchor

Fiscal Note

The source of the additional funding will likely be Solid Waste (Disposal Fund) Revenue Bonds. Discussions are under way with Finance and the Office of Management and Budget pursuant to this option, but it may change if another financing method is more advantageous.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Northeast Maryland Waste Disposal Authority (NMWDA), Maryland Department of the Environment (MDE), Department of Permitting Services, Health and Human Services, the Maryland-National Capital Park and Planning Commission, the U.S. Army Corps of Engineers, the Gude Landfill Concerned Citizens (GLCC), County social service agencies, and adjacent property owners.
Download & Explore
Budget Snapshot
$61.75M Total
Expenditures/Funding
$58.93M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP801801
Date Last Modified01/03/20
Administering AgencyEnvironmental Protection
CategoryRecycling and Resource Management
SubCategoryRecycling and Resource Management
Planning AreaUpper Rock Creek Watershed
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision69551363707479545677193290587785490
Land00000000000
Site Improvements and Utilities00000000000
Construction547910054133017558105611120098105004658
Other00000000000
Total Expenditures61746136370758928456183291149312105106875858748
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Current Revenue: Solid Waste Disposal287001363707266304561832978450000
Long-Term Financing00000000000
Revenue Bonds33046003229800364812105106875858748
Total Funding Sources61746136370758928456183291149312105106875858748
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY18
Appropriation FY 22 Request10955
Last FY's Cost Estimate28700
Cumulative Appropriation9900
Expenditure / Encumbrances1796
Unencumbered Balance8104