Description

This project provides for the relocation of surface parking from Wall Local Park and the Kennedy Shriver Aquatic Center (KSAC) to an adjacent parking garage on private property and the development on an interim park, as suggested in the White Flint Sector Plan. The adjacent property owner, Stonebridge, has an approved Sketch Plan, Preliminary Plan and Phase 1 Site Plan for a project that will include three life sciences buildings totaling approximately 660,000 square feet and a parking garage. As a condition of their approvals, Stonebridge is required to construct and lease to Montgomery County for 50 years 104 parking spaces within the proposed parking garage, to be used by visitors to KSAC, Wall Local Park and the Josiah Henson Museum. The County will have access to an additional 150 parking spaces as needed for special events. The parking garage will be linked to KSAC and Wall Park through a public drive and pedestrian paths. Once the garage is completed, Stonebridge will remove the surface parking area and create an interim park with large green spaces and loop trails. An urban park with varied amenities will be planned by Maryland-National Capital Park and Planning Commission in a future CIP.
project image
anchor

Phase

Planning Stage

Status

Pending Closeout
anchor
Budget Snapshot
$1.11M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Start of construction is dependent on developer timing.
anchor

Justification

The White Flint Sector Plan was approved by Council in 2010. This plan allows for significantly higher density than the existing development. Along with providing a more walkable area through newly programmed capital roads, streetscape, and biking facilities projects, there is a great need for open space that can be easily accessed by both the urban dwellers moving into this dense redevelopment area and by the local community. Wall Park could provide that open space now and will eventually provide an urban park with varied amenities, but only if the surface parking is removed. The roads adjacent to this site have been reconfigured. As part of the Stonebridge project, there is an opportunity to have the surface parking relocated within their garage.
anchor

Coordination

Department of General Services, Department of Transportation, Department of Permitting Services, Department of Recreation, Maryland-National Capital Park and Planning Commission
Budget Snapshot
$1.11M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP721801
Date Last Modified12/23/25
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision5656000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other10503104700000000
Total Expenditures110659104700000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds106013104700000000
PAYGO4646000000000
Total Funding Sources110659104700000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY18
Appropriation FY 28 Request0
Last FY's Cost Estimate1106
Cumulative Appropriation1106
Expenditure / Encumbrances59