The Kennedy Shriver Aquatic Center opened in 1989. It consists of a 50 meter competitive swimming and diving pool, a 200 foot water flume, a separate leisure pool with two hydrotherapy areas, and a diving tower. Since its opening, the center has had problems related to the movement and condensation of moist indoor air through the building's exterior masonry walls, resulting in roof leakage throughout the building. The original scope of the project was to remove and restore existing windows and louvers; remove the 4-inch masonry veneer block throughout the facility, and correct louvers, windows, and penetration flashings; install spray-applied wall insulation functioning as both air/vapor barrier system; install new exterior masonry veneer wall system; and replace the existing roof. During the design evaluation of the entire facility, a structural review was performed for the existing conditions and it was determined that the existing exterior walls will require significantly greater structural modifications than known prior to the evaluation, which has increased the project scope, budget, and schedule to complete the work. In addition, it was determined that the pool equipment and the HVAC systems were also at the end of useful life and also require full system replacements. The Office for Americans with Disabilities Act (ADA) Compliance in the Department of General Services also conducted a full review and design for implementation and remediation of all non-compliance issues at the Kennedy Shriver Aquatic Center. Taken in totality, the facility will require closure for a minimum of eighteen (18) months. Closure of the aquatic center is being coordinated with the Recreation Department and other CIP projects, including MLK Aquatic Centers and the anticipated opening of the South County Regional Recreation and Aquatic Center (Winter 2022), to limit the impact of closed indoor facilities on Recreation patrons. In order to facilitate a longer closure period for the Kennedy Shriver Aquatic Center project, a water heating system will be installed and weatherization of the shower rooms improved at the Glenmont Outdoor Pool to allow for extended season use of the outdoor pool both prior to Memorial Day and after Labor Day. These improvements will facilitate swim and revenue generating activities that would otherwise be eliminated or harmed by the extended closure of the Kennedy Shriver Aquatics Center.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$32.64M Total
Expenditures/Funding
$31.3M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design work started in FY22 with some construction investigation continuing in FY23. Construction scheduled to start in FY24.
anchor

Cost Change

Cost increases reflect additional costs to achieve a Net Zero goal and to extend the usability of the Glenmont Pool to limit the community impact of the KSAC closure during renovation.
anchor

Justification

During the design evaluation of the entire facility, a structural review was performed for the existing conditions and it was determined that the existing exterior walls will require significantly greater structural modifications than known prior to the evaluation, which has increased the project scope, budget, and schedule to complete the work. In addition, it was determined that the pool equipment and the HVAC systems were also at the end of useful life and also require full system replacements. The Office for Americans with Disabilities Act (ADA) Compliance in DGS also conducted a full review and design for implementation and remediation of all non-compliance issues at the Kennedy Shriver Aquatic Center.
anchor

Other

The refurbishment part of this project will be funded by Recreation Facilities Refurbishment (P722105).
anchor

Coordination

Department of General Services, Department of Recreation, Office of Management and Budget, Bethesda/Chevy Chase Regional Services Center, and Maryland-National Capital Park and Planning Commission.
Budget Snapshot
$32.64M Total
Expenditures/Funding
$31.3M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP721503
Date Last Modified05/18/23
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision57957234774595149411411141819000
Land00000000000
Site Improvements and Utilities907009073541941934000
Construction25666658025521982154798079981000
Other276002761112712711000
Total Expenditures326447885573129925221716697661845000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds326447885573129925221716697661845000
Total Funding Sources326447885573129925221716697661845000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request3438
Year First AppropriationFY18
Appropriation FY 24 Request830
Last FY's Cost Estimate32644
Cumulative Appropriation30628
Expenditure / Encumbrances2274
Unencumbered Balance28354