Description

The Kennedy Shriver Aquatic Center opened in 1989. It consists of a 50 meter competitive swimming and diving pool, a 200 foot water flume, a separate leisure pool with two hydrotherapy areas, and a diving tower. Since its opening, the center has had problems related to the movement and condensation of moist indoor air through the building's exterior masonry walls, resulting in roof leakage throughout the building. This original scope of the project was to remove and restore existing windows and louvers; remove the 4-inch masonry veneer block throughout the facility, and correct louvers, windows, and penetration flashings; install spray-applied wall insulation functioning as both air/vapor barrier system; install new exterior masonry veneer wall system; and replace the existing roof.
During the design evaluation of the entire facility, a structural review was performed for the existing conditions and it was determined that the existing exterior walls will require significantly greater structural modifications than known prior to the evaluation, which has increased the project scope, budget, and schedule to complete the work. In addition, it was determined that the pool equipment and the HVAC systems were also at the end of useful life and also require full system replacements. The Office for Americans with Disabilities Act (ADA) Compliance in DGS also conducted a full review and design for implementation and remediation of all non-compliance issues at the Kennedy Shriver Aquatic Center. Taken in totality, the facility will require closure for a minimum of eighteen (18) months.
Closure of the aquatic center is being coordinated with the Recreation Department and other CIP projects, including MLK Aquatic Centers (Summer 2020) and the anticipated opening of the South County Regional Recreation and Aquatic Center (721701), to limit the impact of closed indoor facilities on Recreation patrons. In order to facilitate a longer closure period for the Kennedy Shriver Aquatic Center project, a water heating system and improved weatherization of the shower rooms at the Glenmont Outdoor Pool occurred in FY19 which allows for extended season use of the outdoor pool both prior to Memorial Day and after Labor Day. These improvements will facilitate swim and revenue generating activities that would otherwise be eliminated or harmed by the extended closure of the Kennedy Shriver Aquatics Center.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$27.74M Total
Expenditures/Funding
$27.34M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design work to begin in early 2021 with construction scheduled for spring 2022 through fall 2024.
anchor

Cost Change

Renovation costs are deferred by one fiscal year, with completion scheduled for FY25.
anchor

Justification

During the design evaluation of the entire facility, a structural review was performed for the existing conditions and it was determined that the existing exterior walls will require significantly greater structural modifications than known prior to the evaluation, which has increased the project scope, budget, and schedule to complete the work. In addition, it was determined that the pool equipment and the HVAC systems were also at the end of useful life and also require full system replacements. The Office for Americans with Disabilities Act (ADA) Compliance in DGS also conducted a full review and design for implementation and remediation of all non-compliance issues at the Kennedy Shriver Aquatic Center.
anchor

Coordination

Department of General Services, Department of Recreation, Office of Management and Budget, Bethesda/Chevy Chase Regional Services Center, and Maryland-National Capital Park and Planning Commission.
Budget Snapshot
$27.74M Total
Expenditures/Funding
$27.34M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP721503
Date Last Modified05/19/20
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision9927319639545700254309220358941850
Land00000000000
Site Improvements and Utilities40500405013108284000
Construction17202170171850427332413434000
Other202002020654142000
Total Expenditures27736336632733770070037951606358941850
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds27736336632733770070037951606358941850
Total Funding Sources27736336632733770070037951606358941850
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26
Cost Savings223----32191
Offset Revenue-------
NET IMPACT223----32191
Full Time Equivalent (FTE) ------
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY18
Appropriation FY 22 Request18954
Last FY's Cost Estimate8436
Cumulative Appropriation8236
Expenditure / Encumbrances964
Unencumbered Balance7272