Description

This project will provide for a comprehensive rehabilitation of this historic library to include conversion of the attic into a finished second floor, renovation of the first floor, and the addition of a finished basement, an elevator, Americans with Disabilities Act (ADA) compliant restrooms, and egress stairs. The rehabilitated facility will be able to accommodate more attendees and more types of programming and services than are possible in the current facility.
project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$3.1M Total
Expenditures/Funding
$2.75M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

A draft Concept Plan was reviewed by the County and the Noyes Children's Library Foundation in the Summer of 2013 and agreed upon as the basis for the project design. Initial soil bore testing was completed in late Fall 2013, indicating there were no major problems anticipated. Design began in FY17, and construction will commence when the necessary funds for the complete project are successfully raised by the Noyes Children's Library Foundation. The project has been submitted to the Maryland Historic Trust (MHT) for the review and creation of a Memorandum Of Agreement (MOA) between the MHT, the County, and the Foundation. The MOA is expected to be helpful for private fundraising.
anchor

Justification

The Noyes Library is a small, historically designated library with services specifically focused on Pre-Kindergarten education and Early Childhood (infants through approximately age 8). The small scale and intimate setting of the library are unique and provide a signature experience for children, but the building is not ADA compliant. In 2010, the County proposed a modest effort that would have addressed the ADA issues in the most basic manner possible, as well as made small changes to the library layout that would have positively impacted programming and service offerings. Since that time, the County and the Foundation discussed a more comprehensive rehabilitation of the Noyes Library for Young Children that preserved the library's unique, small-scale, intimate experience, while making substantial improvements to the building that supported use by persons with disabilities, new space for program preparatory and collection work by staff, and additional space for programs. The County Executive is proposing, via this project, a partnership to support this enhanced vision of the Noyes Library for Young Children.
anchor

Fiscal Note

The project is to be funded by County General Obligation (GO) Bonds and private funds that will be raised by the Noyes Children's Library Foundation according to the requirements of the Memorandum of Understanding (MOU) between the County and the Noyes Children's Library Foundation which codifies the fundraising and project plan. In addition, Current Revenue funding of $300,000 in FY17 and $200,000 in FY18 has been moved from Capital Improvement Grants for the Arts and Humanities from Cost Sharing project P720601. The construction phase will not begin until the Noyes Children's Library Foundation completes its fund raising and provides the construction funding in full to the County.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Department of Public Libraries, Department of General Services, Noyes Children's Library Foundation, Maryland-National Capital Park and Planning Commission, Montgomery County Parks, Mid-County Regional Services Center, Washington Suburban Sanitary Commission, Pepco, Town of Kensington Park, Maryland Historic Trust.
Budget Snapshot
$3.1M Total
Expenditures/Funding
$2.75M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP711704
Date Last Modified01/30/18
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryLibraries
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
Planning, Design and Supervision61579271265265000000
Land00000000000
Site Improvements and Utilities30003030000000
Construction23500023502350000000
Other10500105105000000
Total Expenditures31007927127502750000000
FUNDING (000s)
Funding SourceTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
Contributions16000016001600000000
Current Revenue: General50000500500000000
G.O. Bonds100079271650650000000
Total Funding Sources31007927127502750000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24
Maintenance35-77777
Energy30-66666
Program-Staff925-185185185185185
Program-Other5-11111
NET IMPACT995-199199199199199
Full Time Equivalent (FTE) -2.32.32.32.32.3
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 19 Request0
Year First AppropriationFY17
Appropriation FY 20 Request0
Last FY's Cost Estimate3100
Cumulative Appropriation3100
Expenditure / Encumbrances81
Unencumbered Balance3019