Description

Projections indicate that student enrollment at Greencastle Elementary School will exceed capacity by the end of the six-year planning period. As part of the FY2023-2028 CIP, an additional $2.5 million from the county executive's Prevailing Wage and Built to Learn Act PDFs was included in this project to maximize state aid. An FY 2023 appropriation was approved for planning funds. An FY 2024 appropriation is requested for construction funds and an amendment to the FY 2023-2028 CIP is requested for additional funds due to the impact on the construction industry as a result of the Covid-19 pandemic. This addition project is scheduled to be completed August 2025.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$18.5M Total
Expenditures/Funding
$18.5M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$18.5M Total
Expenditures/Funding
$18.5M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP652302
Date Last Modified12/20/22
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision15500015505507712290000
Land00000000000
Site Improvements and Utilities1875001875014504250000
Construction1452000145200388952415390000
Other55000550005500000
Total Expenditures184950018495550611064455390000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds123310012331550611023083363000
State Aid61640061640041372027000
Total Funding Sources184950018495550611064455390000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request1550
Year First AppropriationFY23
Appropriation FY 24 Request16945
Last FY's Cost Estimate14495
Cumulative Appropriation1550
Expenditure / Encumbrances0
Unencumbered Balance1550