anchor Description
Projections indicate that enrollment will exceed capacity through the six-year planning period. In addition, based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. An FY 2021 appropriation was approved for the architectural planning and design for this project. An FY 2022 appropriation was approved for construction funds for this project. An FY 2022 supplemental appropriation and transfer of funds was approved for $5.292 million for this project to address construction cost increases. An FY 2023 appropriation is to complete this project. This Major Capital Project is scheduled to be completed August 2023.