Projections indicate enrollment will exceed capacity for some of the elementary schools in the Bethesda-Chevy Chase and Walter Johnson clusters. Planning expenditures for a new elementary school are programmed in the out-years of the requested FY 2021-2026 CIP. A completion date for this new elementary school will be considered in a future CIP.
anchor

Phase

Status

Active
anchor
Budget Snapshot
$1.2M Total
Expenditures/Funding
$1.2M 6 Year Total
Expenditures/Funding
anchor

Location

Budget Snapshot
$1.2M Total
Expenditures/Funding
$1.2M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP652104
Date Last Modified01/06/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaBethesda-Chevy Chase and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision119500119500006505450
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures119500119500006505450
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds119500119500006505450
Total Funding Sources119500119500006505450
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First Appropriation
Appropriation FY 22 Request0
Last FY's Cost Estimate1195
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0