Description

This project provides funding for County planning, design, installation, and energization of streetlights along US 29 (Columbia Pike) between I-495 and MD 198 (Sandy Spring Road).
anchor

Phase

Planning Stage

Status

New
anchor
Budget Snapshot
$2.84M Total
Expenditures/Funding
$2.84M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design is scheduled for FY24. Utility installation is scheduled for FY25 and FY26.

anchor

Justification

County resolution dated June 25, 1968 requires Montgomery County to provide for the installation of streetlights in those subdivisions that were platted prior to February 1, 1969, when the installation of streetlights was not a requirement of subdivision development. While a limited number of streetlights have been installed over time at most of the intersections within this stretch of US 29, this project will provide additional lighting, per current County standards, to help enhance traffic safety for the motorists and pedestrians alike.
anchor

Fiscal Note

$2.8M in State aid reflects State grants for capital projects in Montgomery County awarded during the 2023 Maryland General Assembly session.
anchor

Disclosures

The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation State Highway Administration (MDOT SHA) and PEPCO.
Download & Explore
Budget Snapshot
$2.84M Total
Expenditures/Funding
$2.84M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502407
Date Last Modified06/08/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryTraffic Improvements
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision1600016001003030000
Land00000000000
Site Improvements and Utilities26800026800012801400000
Construction00000000000
Other00000000000
Total Expenditures2840002840010013101430000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
State Aid2840002840010013101430000
Total Funding Sources2840002840010013101430000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28
Maintenance35--5101010
Energy28--4888
NET IMPACT63--9181818
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First Appropriation
Appropriation FY 24 Request2840
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0