This project provides funding for County planning, design, installation, and energization of streetlights along U.S. 29 (Columbia Pike) between I-495 and MD 198 (Sandy Spring Road).
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$3.08M Total
Expenditures/Funding
$2.88M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design was completed in FY24. Utility installation is scheduled for FY26 through FY28.
anchor

Justification

County resolution dated June 25, 1968, requires Montgomery County to provide for the installation of streetlights in those subdivisions that were platted prior to February 1, 1969, when the installation of streetlights was not a requirement of subdivision development. While a limited number of streetlights have been installed over time at most of the intersections within this stretch of U.S. 29, this project will provide additional lighting, per current County standards, to help enhance traffic safety for the motorists and pedestrians alike.
anchor

Fiscal Note

$2.8 million in State aid reflects State grants for capital projects in Montgomery County awarded during the 2023 Maryland General Assembly session.
anchor

Disclosures

The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation State Highway Administration and Pepco.
Budget Snapshot
$3.08M Total
Expenditures/Funding
$2.88M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502407
Date Last Modified01/10/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryTraffic Improvements
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision400176301941167800000
Land00000000000
Site Improvements and Utilities26830026831610107300000
Construction00000000000
Other00000000000
Total Expenditures30831763028771726115100000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds24003021010510500000
State Aid2843176026671621104600000
Total Funding Sources30831763028771726115100000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance143132626262626
Energy39477777
NET IMPACT182173333333333
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY25
Appropriation FY 28 Request0
Last FY's Cost Estimate3083
Cumulative Appropriation3083
Expenditure / Encumbrances195
Unencumbered Balance2888