Description

This project provides for the extension of Summit Avenue in Kensington from Plyers Mill Road to Farragut Road, improvement of Farragut Road, and reconfiguration of the intersection of Connecticut Ave (MD 185)/University Blvd (MD 193)/Farragut Road.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$27.11M Total
Expenditures/Funding
$13.26M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Final design will begin in FY27. Land acquisition will begin in FY28 and construction will be completed in FY31.
anchor

Justification

This project will provide an alternate route and improve mobility along Connecticut Ave, University Blvd and Plyers Mill Rd. The new roadway will provide easier access to local businesses, add bicycle and pedestrian facilities, and enhance community character.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Maryland DOT State Highway Administration, Maryland Department of the Environment, Maryland Department of Natural Resources, U.S. Army Corps of Engineers, Department of Permitting Services, Utilities, Municipalities, affected communities, Commission on Aging, Commission on People with Disabilities, Montgomery County Pedestrian Safety Advisory Committee

Download & Explore
Budget Snapshot
$27.11M Total
Expenditures/Funding
$13.26M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502311
Date Last Modified03/22/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision18980011630000808355735
Land18150001210000000121006050
Site Improvements and Utilities00000000000
Construction70620000000007062
Other00000000000
Total Expenditures27110001326300008081245513847
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds27110001326300008081245513847
Total Funding Sources27110001326300008081245513847
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First Appropriation
Appropriation FY 24 Request0
Last FY's Cost Estimate27110
Cumulative Appropriation0
Expenditure / Encumbrances0