Description

This project provides for design and construction of a sidewalk along the south side of Tuckerman Lane from Gainsborough Road to the end of the existing sidewalk approximately 380 feet west of Potomac Crest Drive. This project was identified during Facility Planning of the Tuckerman Lane Bicycle and Pedestrian Improvements as a smaller, more affordable improvement that connects Churchill High School to an existing sidewalk segment and which can be implemented more quickly than the broader scope contemplated in the Facility Planning study.
project image
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$0.54M Total
Expenditures/Funding
$0.54M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Facility Planning for Bicycle and Pedestrian Improvements on Tuckerman Lane between Falls Road and Old Georgetown Road was completed in FY22 and preliminary design of the segment (known as Segment 1) between Falls Road and Seven Locks Road is underway. Final design of the sidewalk portion of this segment will be completed in FY27 and construction will occur in FY28. The shared use path, on-road bike lanes and remaining sidewalk in Segment 1 is not programmed as part of this project, nor is preliminary design of Segments 2 (Seven Locks Road to Angus Place), 3 ( Angus Place to Whisperwood Lane) and 4 (Whisperwood Lane to Old Georgetown Road).

anchor

Justification

The purpose of the project is to improve pedestrian and bicyclist safety along Tuckerman Lane. There are no pedestrian facilities on the south side of Tuckerman Lane within the project limits. This segment of Tuckerman Lane is mainly residential where several schools are located, including Herbert Hoover Middle School and Winston Churchill High School.
anchor

Other

This project supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
Budget Snapshot
$0.54M Total
Expenditures/Funding
$0.54M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502302
Date Last Modified03/30/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaPotomac-Cabin John and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision39003900003900
Land81008100008100
Site Improvements and Utilities00000000000
Construction4170041700001492680
Other00000000000
Total Expenditures5370053700002692680
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds5370053700002692680
Total Funding Sources5370053700002692680
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First Appropriation
Appropriation FY 24 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0