up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project will design and implement more dedicated lanes for transit and/or High Occupancy Vehicles (HOV) along the US 29 corridor to improve travel time and reliability. The project will also include improvements at identified "hot spot" locations to improve overall traffic operations along the US 29 corridor.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$6.25M Total
Expenditures/Funding
$4.5M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Preliminary engineering began in FY22 and will be completed in FY24.
anchor

Justification

This project will complement the investment in US 29 Flash and improve transit, carpool, and overall corridor travel time and reliability, performance, and person throughput from MD 198 to the Silver Spring Transit Center. These efforts will support master plan non-auto-drive mode share (NADMS) goals. The project supports the following countywide vision goals: Easier Commutes and a Growing Economy. Approved land use plans in the corridor recommend the implementation of transit lanes along with US 29 Flash. The project is consistent with the Countywide Transit Corridors Functional Master Plan.
anchor

Fiscal Note

Currently, $250,000 is appropriated in FY22 to complete project planning. Alternatives will be presented to the County Council Transportation and Environment Committee for selection and a request to advance to preliminary engineering and appropriate the remaining $1.5 million budgeted for design in FY22.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park and Planning Commission
Budget Snapshot
$6.25M Total
Expenditures/Funding
$4.5M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502201
Date Last Modified05/03/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision62500175045003000150000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures62500175045003000150000000
FUNDING (000s)
Funding SourceTotalThru FY21Est FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds00000000000
Impact Tax62500175045003000150000000
Total Funding Sources62500175045003000150000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request6000
Year First AppropriationFY22
Appropriation FY 24 Request0
Last FY's Cost Estimate6250
Cumulative Appropriation250
Expenditure / Encumbrances0
Unencumbered Balance250