Description

This project provides for the design and construction of a new eight-foot wide shared use path approximately 1 mile of length along the north side of Dale Drive from Georgia Avenue (MD 97) to Colesville Road (US 29). The project also provides minor intersection safety improvements within the project limits to improve existing sight distance and crosswalks.

project image
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$8.45M Total
Expenditures/Funding
$8.45M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design, land acquisition, and construction will be completed in FY22, FY24, and FY26 respectively. The construction will have a duration of 2 years.

anchor

Justification

There are only short segments of sidewalk scattered within the project limits but no continuous pedestrian facilities on this section of Dale Drive, where several school bus stops are located. This section of Dale Drive is also the last missing link of pedestrian facilities on Dale Drive and a connection to the future Purple Line Station on Dale Drive and Wayne Avenue, as well as the Sligo Creek Trail.

The Montgomery County Bicycle Master Plan, approved in November 2018, recommends a shared use path or sidewalk to be added for this section of Dale Drive.

anchor

Other

This project supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
Download & Explore
Budget Snapshot
$8.45M Total
Expenditures/Funding
$8.45M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502109
Date Last Modified05/14/20
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision2156002156644709005262770
Land231200231200708124436000
Site Improvements and Utilities48200482000048200
Construction34990034990000190915900
Other00000000000
Total Expenditures84490084496447097081244327718670
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds84490084496447097081244327718670
Total Funding Sources84490084496447097081244327718670
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request1353
Year First Appropriation
Appropriation FY 22 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0