Description

This project provides for the design and construction of a new eight-foot wide shared use path approximately 1 mile of length along the north side of Dale Drive from Georgia Avenue (MD 97) to Colesville Road (US 29). The project also provides minor intersection safety improvements within the project limits to improve existing sight distance and crosswalks.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$10.22M Total
Expenditures/Funding
$8.86M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design, land acquisition, and construction will be completed in FY22, FY24, and FY26, respectively. The construction will have a duration of 2 years.
anchor

Cost Change

Cost increase due to additional pedestrian connection along south side of Dale Drive from Georgia Avenue to Woodland Drive, drainage improvements and traffic calming measures on Dale Drive within the project limits.
anchor

Justification

There are only short segments of sidewalk scattered within the project limits but no continuous pedestrian facilities on this section of Dale Drive, where several school bus stops are located. This section of Dale Drive is also the last missing link of pedestrian facilities on Dale Drive and a connection to the future Purple Line Station on Dale Drive and Wayne Avenue, as well as the Sligo Creek Trail. The Montgomery County Bicycle Master Plan, approved in November 2018, recommends a shared use path or sidewalk to be added for this section of Dale Drive.
anchor

Other

This project supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
Budget Snapshot
$10.22M Total
Expenditures/Funding
$8.86M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502109
Date Last Modified10/05/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision22408914628870119435333000
Land122100122170851300000
Site Improvements and Utilities61200612061200000
Construction61420061420028423300000
Other00000000000
Total Expenditures102158914628862708124432773633000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds102158914628862708124432773633000
Total Funding Sources102158914628862708124432773633000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request1221
Year First AppropriationFY21
Appropriation FY 24 Request7641
Last FY's Cost Estimate10215
Cumulative Appropriation2574
Expenditure / Encumbrances1388
Unencumbered Balance1186