Description

This project will construct a new Bus Rapid Transit (BRT) line on US 29 from Burtonsville Park-and-Ride lot to the Silver Spring Transit Center. The project will build 18 new BRT station platforms with level boarding and off-board fare payment, purchase 14 new 60-foot articulated vehicles, implement Transit Signal Priority at 15 intersections, and construct improved bicycle and pedestrian infrastructure, including 10 new Capital Bikeshare stations. The new BRT service will use the existing bus-on-shoulder lanes on US 29 in the northern section of the corridor and operate in mixed traffic in the southern section of US 29 and along Lockwood Drive, Stewart Lane, Briggs Chaney Road, and Castle Boulevard.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$31.55M Total
Expenditures/Funding
$0.55M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Project planning was completed in FY18 in project #501318 and design was completed in early FY19. Construction commenced in FY19 and will be completed in FY20, with revenue service starting in FY20. WSSC water line work to continue into FY21.
anchor

Cost Change

$550,000 has been added in FY21 to account for the portion of the water and sewer relocation cost that will be paid by the Washington Suburban Sanitary Commission under a 50% cost sharing arrangement with the County. The previous project cost estimate only accounted for the County-funded portion of water/sewer relocation cost.
anchor

Justification

The project will transform mobility options with the implementation of a 14-mile, premium, branded, limited-stop BRT service along US 29. This new service will improve transit travel time and increase opportunity for a broad range of users, including a significant number of minority and low-income riders living along a highly congested corridor. The project will improve passenger transit mobility by connecting riders to high density housing and employment centers. This project is vital to the success of significant new private development and employment in the adopted White Oak Science Gateway Master Plan.Plans & Studies: MCDOT Countywide Bus Rapid Transit Study, Final Report (July 2011); County Executive's Transit Task Force (May 2012); Countywide Transit Corridors Functional Master Plan (November 2013); MCDOT US 29 Bus Rapid Transit Project Description Report (March 2017); Maryland Department of Transportation/Maryland Transit Administration US 29 Bus Rapid Transit Corridor Planning Study (April 2017).
anchor

Other

Prior to FY19, $6.5 million for Planning and Design and $500,000 in grant management was included in PDF 501318: Rapid Transit System (renamed to Bus Rapid Transit System Development in FY19). Since Planning and Design were close to completion at the end of FY18, only funds for the construction phase of the project (FY19 and 20) have been moved to this new PDF.
anchor

Fiscal Note

The project is receiving $10 million of Federal funds through the Transportation Infrastructure Generating Economic Recovery (TIGER) program. The Federal funds will be used towards station and pedestrian/bicycle infrastructure construction. The Maryland Department of Transportation Consolidated Transportation Program (CTP) for 2014-2019 provided $10 million for County Rapid Transit System planning, a portion of which was used to begin facility planning on the US 29 corridor. Reflects reallocation of $1.3 million in GO Bonds from the ADA Compliance: Transportation project (#509325) to cover ADA sidewalk upgrades.In FY20, Funding switch of $2 million from Contributions to GO Bonds.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park and Planning Commission. Special Projects Legislation (Expedited Bill No. 20-18) was adopted by Council June 19, 2018.
Download & Explore
Budget Snapshot
$31.55M Total
Expenditures/Funding
$0.55M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501912
Date Last Modified01/03/20
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision13357778550550000000
Land2000109189100000000
Site Improvements and Utilities32150321500000000
Construction110004206679400000000
Other1400001400000000000
Total Expenditures31550432226678550550000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Contributions00000000000
Federal Aid95004322517800000000
G.O. Bonds55000550000000000
Impact Tax20000200000000000
Intergovernmental55000550550000000
Short-Term Financing1400001400000000000
Total Funding Sources31550432226678550550000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request550
Year First AppropriationFY19
Appropriation FY 22 Request0
Last FY's Cost Estimate31000
Cumulative Appropriation31000
Expenditure / Encumbrances27834
Unencumbered Balance3166