Description

This project provides for the replacement of the existing Beach Drive Bridge over Silver Creek. The existing bridge, built in 1964, consists of three steel plate arches. The bridge provides a 24'-0" wide clear roadway with a 7'-0" Rock Creek Trail on the north side and has two 1'-9" parapets. The proposed replacement bridge includes a single span prestressed concrete slab beam structure carrying a 22'-0" roadway and a 5'-4" shoulder on each side. This width will allow for the implementation of safe on-road bicycling in accordance with the Master Plan. The Rock Creek Trail will be relocated to cross Silver Creek approximately 90 feet north of the proposed Beach Drive Bridge. This will improve safety by separating the pedestrian and light-use bicycle traffic from the vehicular traffic. The project includes approach roadway work at each end of the bridge as necessary to tie in to the existing roadway. The bridge and road will be closed to traffic during construction. In order to maintain pedestrian traffic on Rock Creek Trail during construction, the pedestrian bridge, and its approaches will be constructed prior to the removal of the existing Beach Drive Bridge. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$3.85M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 5,500 vehicles and the roadway capacity will not change as a result of this project.
anchor

Fiscal Note

The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal Aid. Fund transfer in GO Bonds to Good Hope Rd., P501902 of $350,000 in FY25.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
Budget Snapshot
$3.85M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501903
Date Last Modified01/06/25
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision807807000000000
Land50500000000
Site Improvements and Utilities00000000000
Construction30401978106200000000
Other00000000000
Total Expenditures38522785106700000000
FUNDING (000s)
Funding SourceTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Federal Aid2790197082000000000
G.O. Bonds106281524700000000
Total Funding Sources38522785106700000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY20
Appropriation FY 26 Request0
Last FY's Cost Estimate4202
Cumulative Appropriation3852
Expenditure / Encumbrances2785
Unencumbered Balance1067