up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the design and construction of a new eight-foot wide sidepath along the west side of Good Hope Road over 4,500 feet of length from Windmill Lane to Rainbow Drive in Cloverly. The project also provides a pedestrian bridge that is 40-foot long and eight-foot wide at the intersection of Good Hope Road and Hopefield Road. The project site is located within the Upper Paint Branch Special Protection Area.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$6.28M Total
Expenditures/Funding
$1.06M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design was completed in FY21. Land acquisition will be completed in FY24. Construction will be completed in FY25.
anchor

Cost Change

Project reflects FY24 supplemental to cover cost increases.
anchor

Justification

The project enhances the pedestrian safety along Good Hope Road from Windmill Lane to Rainbow Drive. The pedestrian bridge addresses a section of the road where there is no sidewalk or shoulder for pedestrians. The Cloverly Master Plan, adopted in July 1997, recommends a sidewalk along Good Hope Road. The project was also requested by the Good Hope Estates Civic Association.
anchor

Other

The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Fiscal Note

A supplemental appropriation was approved in FY24 for $562k for additional construction and construction management costs.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Maryland Department of the Environment
Budget Snapshot
$6.28M Total
Expenditures/Funding
$1.06M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501902
Date Last Modified01/09/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCloverly-Norwood
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision20801596307177177000000
Land77232344900000000
Site Improvements and Utilities4904900000000
Construction338112500880880000000
Other00000000000
Total Expenditures62821920330510571057000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds59181556330510571057000000
Impact Tax364364000000000
Total Funding Sources62821920330510571057000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Maintenance25-55555
Energy5-11111
NET IMPACT30-66666
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY19
Appropriation FY 26 Request0
Last FY's Cost Estimate6282
Cumulative Appropriation6282
Expenditure / Encumbrances2178
Unencumbered Balance4104