Description

This project provides for the design and construction of a new eight-foot wide sidepath along the west side of Good Hope Road over 4,500 feet of length from Windmill Lane to Rainbow Drive in Cloverly. The project also provides a pedestrian bridge that is 40-feet long and eight-feet wide at the intersection of Good Hope Road and Hopefield Road. The project site is located within the Upper Paint Branch Special Protection Area.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$6.63M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design was completed in FY21. Land acquisition was completed in FY23. Construction was completed in FY25.
anchor

Justification

The project enhances the pedestrian safety along Good Hope Road from Windmill Lane to Rainbow Drive. The pedestrian bridge addresses a section of the road where there is no sidewalk or shoulder for pedestrians. The Cloverly Master Plan, adopted in July 1997, recommends a sidewalk along Good Hope Road. The project was also requested by the Good Hope Estates Civic Association.
anchor

Other

The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Fiscal Note

A supplemental appropriation was approved in FY24 for $562,000 for additional construction and construction management costs. A fund transfer of $350,000 from the Beach Drive Bridge project (#501903) was completed in FY25 for costs associated with energization of street lights and additional PDS cost. FY25 actuals funding switch between GO Bonds and Impact Taxes.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Maryland Department of the Environment
Download & Explore Project Details
Budget Snapshot
$6.63M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP501902
Date Last Modified01/11/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCloverly-Norwood
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision2320209722300000000
Land59939920000000000
Site Improvements and Utilities194194000000000
Construction35193519000000000
Other00000000000
Total Expenditures6632620942300000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Contributions00000000000
G.O. Bonds1965155740800000000
Impact Tax46524652000000000
Intergovernmental1501500000000
Total Funding Sources6632620942300000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance30555555
Energy6111111
NET IMPACT36666666
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY19
Appropriation FY 28 Request0
Last FY's Cost Estimate6632
Cumulative Appropriation6632
Expenditure / Encumbrances6441
Unencumbered Balance191