Description

This project provides for a continuous sidewalk along the north side of Franklin Ave from Colesville Rd (US 29) to University Blvd (MD 193). The project includes 4,600 linear feet of sidewalk, new curb and gutter, and storm drains.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$3.3M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Construction is scheduled for completion in FY24.
anchor

Justification

This project is needed to construct a missing segment of sidewalk along the north side of Franklin Ave. Continuous and safe pedestrian access will be provided to existing sidewalks and bikeways, transit stops, churches, schools and public facilities in the Silver Spring area. This project conforms to the 2000 East Silver Spring Master Plan.
anchor

Other

Preliminary Design was completed in the Facility Planning - Transportation project in FY15. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Transit Administration, Maryland Department of Transportation, State Highway Administration, Office of the County Executive, Maryland-National Capital Park and Planning Commission, Department of General Services, Department of Permitting Services, Silver Spring Transportation Management District, Silver Spring Chamber of Commerce.
Budget Snapshot
$3.3M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501734
Date Last Modified01/10/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision925925000000000
Land865086500000000
Site Improvements and Utilities00000000000
Construction15100151000000000
Other00000000000
Total Expenditures3300925237500000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds3300925237500000000
Total Funding Sources3300925237500000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY20
Appropriation FY 26 Request0
Last FY's Cost Estimate3300
Cumulative Appropriation3300
Expenditure / Encumbrances3044