Description

This project provides for a continuous sidewalk along the north side of Franklin Ave from Colesville Rd (US 29) to University Blvd (MD 193). The project includes 4,600 linear feet of sidewalk, new curb and gutter, and storm drains.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$3.3M Total
Expenditures/Funding
$2.95M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Final design will begin in FY20, land acquisition will begin in FY21, and construction will begin in FY22.
anchor

Justification

This project is needed to construct a missing segment of sidewalk along the north side of Franklin Ave. Continuous and safe pedestrian access will be provided to existing sidewalks and bikeways, transit stops, churches, schools and public facilities in the Silver Spring area. This project conforms to the 2000 East Silver Spring Master Plan.
anchor

Other

Preliminary Design was completed in the Facility Planning - Transportation project in FY15. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Transit Administration, Maryland Department of Transportation, State Highway Administration, Office of the County Executive, Maryland-National Capital Park and Planning Commission, Department of General Services, Department of Permitting Services, Silver Spring Transportation Management District, Silver Spring Chamber of Commerce.
Download & Explore
Budget Snapshot
$3.3M Total
Expenditures/Funding
$2.95M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501734
Date Last Modified12/31/19
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision914034656835521300000
Land8650086541245300000
Site Improvements and Utilities00000000000
Construction15210015210152100000
Other00000000000
Total Expenditures330003462954767218700000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds330003462954767218700000
Total Funding Sources330003462954767218700000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request1220
Year First AppropriationFY20
Appropriation FY 22 Request1734
Last FY's Cost Estimate3300
Cumulative Appropriation346
Expenditure / Encumbrances0
Unencumbered Balance346