This project provides for the design, land acquisition, and construction of roadway improvements along East Gude Drive from Crabbs Branch Way to Southlawn Lane to increase mobility and improve vehicular and pedestrian safety. The improvements will: (1) add a westbound lane (800 linear feet) from Calhoun Drive to Crabbs Branch Way; (2) extend the length of the eastbound taper east of Calhoun Drive (500 linear feet) to west of Incinerator Lane; (3) provide an east-to-northbound left turn lane (300 linear feet) at Dover Road; (4) construct the missing section of sidewalk on the north side of East Gude Drive from west of Incinerator Lane to east of Calhoun Drive (550 linear feet) and (5) install six-foot wide sidewalk connectors from each bus stop on the north side of East Gude Drive to the nearest intersection.
project image
anchor

Phase

Final Design Stage

Status

Pending Closeout
anchor
Budget Snapshot
$6.03M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The Average Daily Traffic (ADT) on East Gude Drive for the year 2025 is forecasted to be about 60,000.
anchor

Estimated Schedule

Project will be completed in FY24.
anchor

Justification

The project is needed to improve roadway mobility and safety, provide for alternate modes of transportation and improve pedestrian connectivity and safety by constructing missing sidewalk sections on the north side.
anchor

Fiscal Note

FY22 funding switch of $2,798,000 from G.O. Bonds to Impact Tax to reflect FY22 actuals.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Utility Companies, Department of Permitting Services, City of Rockville
Budget Snapshot
$6.03M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501309
Date Last Modified12/21/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision27642764000000000
Land105592712800000000
Site Improvements and Utilities415041500000000
Construction1793166113200000000
Other00000000000
Total Expenditures6027535267500000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds2125145067500000000
Impact Tax39023902000000000
Total Funding Sources6027535267500000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Energy6111111
NET IMPACT6111111
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY16
Appropriation FY 26 Request0
Last FY's Cost Estimate6027
Cumulative Appropriation6027
Expenditure / Encumbrances5966
Unencumbered Balance61