Description

This project provides for the planning, design, and renovation/modification of the Montgomery County Detention Center (MCDC) for use primarily as a short-term holding and central processing facility. The original building was built in 1961 with the High Rise/Tower and other modular units constructed thereafter. The project provides for demolition of dilapidated out of operation structures including demolition of the High Rise/Tower, five vacant modular units and the CIU pod which is currently used by HHS. Prior to demolition, the existing utilities will be rerouted, and a new utility structure will be built. HHS will be relocated from the CIU pod to a temporary location in the occupied building while renovation of their final location is completed. Renovation of other select areas of the building is included. The work will be done in phases due to the complexity of the project and the need to keep the main building operational throughout the project.
project image
anchor

Phase

Planning Stage

Status

New
anchor
Budget Snapshot
$4.79M Total
Expenditures/Funding
$4.79M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Construction is expected to begin in early 2021.
anchor

Justification

Council Resolution 13-356, passed by the Montgomery County Council in 1995, approved a two-jail system which includes the Montgomery County Correctional Facility (MCCF) located in Boyds and the Montgomery County Detention Center (MCDC) in Rockville. The current MCDC was the designated location for the intake and release of all inmates. Functions included the Central Processing Unit (CPU); the Maryland County District Court Commissioners; evaluation for pre-trial services, medical and mental health assessments; centralized records and storage; and DOCR training. The facility also provides beds for housing inmates during intake process. After many years of service, the building is no longer in good repair and does not meet all the current State and County requirements. To meet the requirements of the Council Resolution, MCDC needs to be replaced or renovated sufficiently in order to operate fully until a future new Criminal Justice Center can be constructed in its place. To provide an immediate response to these issues the project proposes a limited renovation of the buildings remaining after demolition of unused structures. As part of the renovation, and in order to continue to provide these services, specific changes will be implemented to meet current State and County requirements. In addition, a general refresh of spaces is needed to provide a conducive workspace for the staff for the immediate future. Demolition of five vacant modular structures and the partially occupied CIU pod will save maintenance and energy costs. Annual maintenance costs for this facility routinely reach and sometimes exceed $100,000.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Department of Correction and Rehabilitation, Department of General Services, Department of Health and Human Services, Department of Technology Services, Department of Police, Montgomery County Fire and Rescue Service, Sheriff's Office, District Court of Maryland, State of Maryland, City of Rockville, Washington Gas, and PEPCO
Download & Explore
Budget Snapshot
$4.79M Total
Expenditures/Funding
$4.79M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP422102
Date Last Modified06/15/20
Administering AgencyGeneral Services
CategoryPublic Safety
SubCategoryCorrection and Rehabilitation
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision9810098174923200000
Land00000000000
Site Improvements and Utilities30700307307000000
Construction2902002902724217800000
Other6010060150010100000
Total Expenditures47910047912280251100000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds47910047912280251100000
Total Funding Sources47910047912280251100000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26
Energy-612---153-153-153-153
NET IMPACT-612---153-153-153-153
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request4559
Year First AppropriationFY21
Appropriation FY 22 Request232
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0