up
Budget Year / Version:  
anchor
anchor
anchor

Description

Tilden Middle School was originally built in 1967, was closed in 1986 and reopened in 1991. When the school reopened in 1991, facility improvements were done, but not a full modernization. Scheduling of this modernization is consistent with the MCPS long-range plans to renew aging facilities on a rational and periodic basis. The modernization will include an addition to this facility due to projected enrollment growth. Due to fiscal constraints, the middle school modernization program was delayed two years in the adopted FY 2013-2018 CIP. While planning funds remain on schedule, due to fiscal constraints, construction funds for this project were delayed one year in the approved FY2015-2020 CIP. The Board of Education's requested FY2015-2020 Amended CIP reinstated the construction schedule previously requested by the Board. Due to fiscal constraints, the County Council did not approve the Board's request. An FY 2016 appropriation was approved for planning funds. An FY 2019 appropriation will be requested for construction funds. The Board of Education in May 2015 approved the collation of Tilden MS with the Rock Terrace School. An FY 2019 appropriation will be requested for construction funds. This revitalizatoin/expansion project is now scheduled to be completed by August 2020. An FY 2018 appropriation was approved to accelerate the site work for this project. An FY 2019 appropriation was approved for construction funds. This project is scheduled to be completed September 2020.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$88.65M Total
Expenditures/Funding
$19.48M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$88.65M Total
Expenditures/Funding
$19.48M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP096511
Date Last Modified12/02/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision57345734000000000
Land00000000000
Site Improvements and Utilities73787378000000000
Construction734275395201947519475000000
Other21082108000000000
Total Expenditures886476917201947519475000000
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds1706612306047604760000000
Recordation Tax5411354113000000000
State Aid17468275301471514715000000
Total Funding Sources886476917201947519475000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY16
Appropriation FY 22 Request0
Last FY's Cost Estimate88647
Cumulative Appropriation88647
Expenditure / Encumbrances0
Unencumbered Balance88647