Description

The Kennedy Shriver Aquatic Center opened in 1989. It consists of a 50-meter competitive swimming and diving pool, a 200-foot water flume, a separate leisure pool with two hydrotherapy areas, and a diving tower. Since its opening, the center has had problems related to the movement and condensation of moist indoor air through the building's exterior masonry walls, resulting in roof leakage throughout the building. The original scope of the project was to remove and restore existing windows and louvers; remove the 4-inch masonry veneer block throughout the facility, and correct louvers, windows, and penetration flashings; install spray-applied wall insulation functioning as both air/vapor barrier system; install a new exterior masonry veneer wall system; and replace the existing roof. During the design evaluation of the entire facility, a structural review was performed for the existing conditions, and it was determined that the existing exterior walls will require significantly greater structural modifications than were known prior to the evaluation, which has increased the project scope, budget, and schedule to complete the work. In addition, it was determined that the pool equipment and the HVAC systems were at the end of their useful life and also require full system replacements. The Office for Americans with Disabilities Act (ADA) Compliance in the Department of General Services (DGS) also conducted a full review and design for implementation and remediation of all non-compliance issues at the Kennedy Shriver Aquatic Center. Taken in totality, the facility will require closure for a minimum of (24) months. Closure of the aquatic center is being coordinated with the Department of Recreation and other CIP projects, including MLK Aquatic Center and the opening of the Silver Spring Recreation and Aquatic Center, to limit the impact of closed indoor facilities on patrons. In order to facilitate a longer closure period for the Kennedy Shriver Aquatic Center project, a water heating system has been installed, and weatherization of the shower rooms will be improved at the Glenmont Outdoor Pool to allow for extended season use of the outdoor pool both prior to Memorial Day and after Labor Day. These improvements will facilitate swim and revenue generating activities that would otherwise be eliminated or harmed by the extended closure of the Kennedy Shriver Aquatics Center.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$33.92M Total
Expenditures/Funding
$0.6M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design work started in FY22, with some construction investigation continuing in FY24. Construction started in FY25 in coordination with the completion of the Silver Spring Recreation and Aquatic Center, which was fully operational before closing the Kennedy Shriver Aquatic Center for renovation.
anchor

Cost Change

Cost increase reflects project escalation.
anchor

Other

The refurbishment part of this project is funded by Recreation Facilities Refurbishment - project (P722105) as well as Recreation Facilities Refurbishment-Indoor Pools (P722506). The Netzero part of the project is funded by Altagas-WGL Merger Fund (P362106) and Elevator Replacement part is funded by Elevator Modernization (P509923).
anchor

Coordination

Department of General Services, Department of Recreation, Bethesda-Chevy Chase Regional Services Center, Maryland-National Capital Park and Planning Commission. Special Capital Projects Legislation [Bill No. 15-22] was adopted by Council July 25, 2022.
Budget Snapshot
$33.92M Total
Expenditures/Funding
$0.6M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP721503
Date Last Modified12/30/25
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision585037621492596596000000
Land00000000000
Site Improvements and Utilities230023000000000
Construction2755193981815300000000
Other2881127700000000
Total Expenditures339191317120152596596000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds339191317120152596596000000
Total Funding Sources339191317120152596596000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request354
Year First AppropriationFY18
Appropriation FY 28 Request0
Last FY's Cost Estimate33919
Cumulative Appropriation33565
Expenditure / Encumbrances30014
Unencumbered Balance3551