up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Greentree Road bridge No. M-0180 over Bulls Run in Bethesda. The proposed replacement includes the removal and replacement of the existing bridge structure and a temporary bridge to accommodate pedestrian and bicycle traffic during construction. The proposed work also includes sidewalk and bus stop improvements and approximately 330' of approach roadway work at each end of the bridge. The road and bridge will remain open to vehicular traffic during construction.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$5M Total
Expenditures/Funding
$5M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The Average Daily Traffic (ADT) is approximately 6,516 vehicles. The roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

The design is expected to be completed in FY28. Construction is expected to begin in FY28 and complete in FY30. The estimated duration of construction is 15 months.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the public. The 2020 Bridge Inspection Report indicated that the existing culvert, which acts as a long span bridge, was in poor condition due to: large areas of spalled concrete, large cracks, exposed and corroded reinforcement steel, and large areas of delamination. The existing bridge is at risk of becoming structurally deficient and must be replaced.
anchor

Fiscal Note

The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal aid funding. The design costs are covered in the Bridge Design project (No. 509132).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, and Bridge Design Project (CIP 509132)
Download & Explore Project Details
Budget Snapshot
$5M Total
Expenditures/Funding
$5M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502704
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaBethesda-Chevy Chase and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision1063001063064635364000
Land80008080000000
Site Improvements and Utilities30000300300000000
Construction3557003557034021011116000
Other00000000000
Total Expenditures500000500038040427361480000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid3489003489030820731108000
G.O. Bonds151100151138096663372000
Total Funding Sources500000500038040427361480000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request380
Year First Appropriation
Appropriation FY 28 Request4620
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0
anchor
Download & Explore Project Details