up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of two failing culverts under Seven Locks Road in front of the historic Scotland AME Zion Church. Work was originally initiated under the Bridge Renovation project (P509753). The existing culverts to be replaced are twin 44" by 72" structural plate pipe arch (SPPA) and a 36" by 56" corrugated metal pipe (CMP). The replacement culverts will be upsized to allow for significantly more flow in order to mitigate flooding risk to the church property.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$4.8M Total
Expenditures/Funding
$4.72M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The Average Daily Traffic (ADT) is approximately 14,224 vehicles. The roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

Property acquisition is scheduled for FY26. Construction is scheduled for FY27 and will be completed in FY28. The estimated duration of construction is 12 months. Project experienced unanticipated utility relocations and negotiations with the Scotland AME Zion Church resulting in design delays.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the traveling public. The 2023 Bridge Inspection Report indicates that the steel culverts have 100 percent invert section loss and are in poor condition. In the past, the historic Scotland AME Church suffered multiple instances of severe flooding resulting in damage to the property. The church is currently undergoing restoration and renovation, including improvements to protect the building from flooding. In 2024, the Montgomery County Departments of Transportation and Permitting Services conducted further study of the area and concluded that increasing conveyance capacity of culverts in front of the church from the current design criteria of a 25-year storm to a 100-year storm would further mitigate risk of flooding to the church property.
anchor

Fiscal Note

The design will be completed in FY26 under Bridge Renovation (CIP 509753).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Scotland AME Zion Church, Montgomery County Department of Permitting Services, and Utilities.
Download & Explore Project Details
Budget Snapshot
$4.8M Total
Expenditures/Funding
$4.72M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502513
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaPotomac-Cabin John and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision9330093366426900000
Land7786900000000
Site Improvements and Utilities20000200200000000
Construction3590003590271987100000
Other00000000000
Total Expenditures480086947233583114000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid00000000000
G.O. Bonds480086947233583114000000
Total Funding Sources480086947233583114000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY25
Appropriation FY 28 Request0
Last FY's Cost Estimate4800
Cumulative Appropriation4800
Expenditure / Encumbrances8
Unencumbered Balance4792
anchor
Download & Explore Project Details