Description

The Silver Spring and Bethesda Secure Bike Parking Facilities will be located at the Silver Spring and Bethesda Metro Stations and will provide a secure area for people biking to park. This will give them the peace-of-mind that their bikes will not be vandalized or stolen while they are parked. Similar facilities have been built at other Metro stations in the region, including College Park, East Falls Church, Whiele-Reston East, and one is under construction at Grosvenor.
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$0.54M Total
Expenditures/Funding
$0.2M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

The Silver Spring Secure Bike Parking Facility will be constructed in FY26. The Bethesda Secure Bike Parking Facility will be constructed in FY28 after Purple Line construction is completed.
anchor

Justification

As the County builds out its low-stress bike network, providing convenient and secure bike parking facilities is critical. If people worry that their bike will be stolen or vandalized while parked, they will likely choose not to bike, even if the bikeways are comfortable and convenient. This project will add secure bike parking facilities at the Silver Spring Transit Center and the Bethesda Metro station, both of which are served by the Metro Red Line and will soon be served by the Purple Line light rail.
anchor

Fiscal Note

These projects are partially funded by a federal earmark covering 80 percent of the cost.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland Transit Administration Purple Line construction, Silver Spring Urban District, Bethesda Urban District, Bethesda Urban Partnership, Montgomery County Parks Department
Download & Explore Project Details
Budget Snapshot
$0.54M Total
Expenditures/Funding
$0.2M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502510
Date Last Modified01/11/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction5350338197019700000
Other00000000000
Total Expenditures5350338197019700000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid4270270157015700000
G.O. Bonds1080684004000000
Total Funding Sources5350338197019700000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance11122222
Energy11122222
NET IMPACT22244444
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY25
Appropriation FY 28 Request197
Last FY's Cost Estimate535
Cumulative Appropriation338
Expenditure / Encumbrances0
Unencumbered Balance338