This project provides for the extension of Summit Avenue in Kensington from Plyers Mill Road to Farragut Road, improvement of Farragut Road, and reconfiguration of the intersection of Connecticut Avenue (MD 185)/University Boulevard (MD 193)/Farragut Road.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$31.49M Total
Expenditures/Funding
$0.99M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Final design will begin in FY32. Land acquisition will start in FY33 and construction will start in FY34.
anchor

Cost Change

Cost increase due to update of previous cost estimate for inflation.
anchor

Justification

This project will provide an alternate route and improve mobility along Connecticut Ave, University Blvd and Plyers Mill Rd. The new roadway will provide easier access to local businesses, add bicycle and pedestrian facilities, and enhance community character.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Maryland State Highway Administration, Maryland Department of the Environment, Maryland Department of Natural Resources, U.S. Army Corps of Engineers, Department of Permitting Services, Utilities, Municipalities, affected communities, Commission on Aging, Commission on People with Disabilities, Montgomery County Pedestrian Safety Advisory Committee

Download & Explore Project Details
Budget Snapshot
$31.49M Total
Expenditures/Funding
$0.99M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502311
Date Last Modified01/09/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision282000990000009901830
Land2149000000000021490
Site Improvements and Utilities00000000000
Construction71800000000007180
Other00000000000
Total Expenditures31490009900000099030500
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds31490009900000099030500
Transportation Special Taxing District00000000000
Total Funding Sources31490009900000099030500
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate31445
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0