This project provides for planning, design, permitting, and construction of a parking garage and other improvements at the Burtonsville Park and Ride lot in support of Flash service on the U.S. 29 corridor. The County is partnering with a private developer who will design and construct a parking garage for the County. The garage will include approximately 250 parking spaces for commuter parking and will be designed to accommodate an addiitonal 250 spaces in the future. The balance of the surface lot will be developed with residential units, including moderately priced dwelling units and workforce units. The Burtonsville Station is the northernmost FLASH station in Montgomery County and is well-situated for park and ride access with direct ramps to U.S. 29 and strong east-west connections via MD 198. With this strategic location, the park-and-ride can serve residents of Montgomery, Prince George's and Howard Counties, increasing transit ridership and lowering traffic demands on U.S. 29 through Montgomery County. Expansion of this park and ride is needed to accommodate future ridership at this station and is part of longer-term plans to extend Flash service into Howard County and to provide all-day service in Burtonsville. The location can also serve as a hub for interconnecting local services to nearby communities like Cloverly, Ashton, Laurel and Maple Lawn. Expansion of public parking capacity at this location may also facilitate a more compelling development vision for County, State and privately owned properties in this part of Burtonsville.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$8M Total
Expenditures/Funding
$2.64M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design and permitting of the garage commenced in FY25. Construction will start in FY27 and be completed by FY28.
anchor

Cost Change

Cost change due to increases for garage construction.
anchor

Justification

In addition to Flash BRT service, Ride On and commuter parking, this facility serves Metrobus and MTA bus services and supports County employee commuting. The park and ride lot has strong access to U.S. 29, but access from Old Columbia Pike and Maryland 198 relies upon connections through the adjacent commercial development. The Burtonsville Crossing Shopping Center is immediately adjacent to the park and ride lot and the rear of the center faces the Flash station. This transit oriented development combines a residential component and a major transit hub on the U.S. 29 corridor.
anchor

Fiscal Note

State aid reflects State grants for capital projects in Montgomery County programmed or preauthorized during the 2020, 2021, and 2023 State General Assembly Sessions.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Department of General Services, Department of Transportation, Office of Intergovernmental Relations, Office of the County Executive, Community Engagement Cluster
Download & Explore Project Details
Budget Snapshot
$8M Total
Expenditures/Funding
$2.64M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502203
Date Last Modified01/06/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaFairland-Beltsville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision90068534141000000
Land00000000000
Site Improvements and Utilities00000000000
Construction71000450026002600000000
Other00000000000
Total Expenditures80006535326412641000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds20000020002000000000
State Aid600065353641641000000
Total Funding Sources80006535326412641000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance750-150150150150150
NET IMPACT750-150150150150150
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request2000
Year First AppropriationFY22
Appropriation FY 28 Request0
Last FY's Cost Estimate6000
Cumulative Appropriation6000
Expenditure / Encumbrances23
Unencumbered Balance5977