up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project will design and implement a dedicated lane for Bus Rapid Transit in the median of US 29 between Tech Road and Sligo Creek Parkway to improve travel time and service reliability. The project will also include an additional lane on the ramp from southbound US 29 to westbound I-495 and feasibility assessments for master planned bicycle facilities along US 29 within the project study limits.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$9.75M Total
Expenditures/Funding
$3.49M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Preliminary engineering began in the fourth quarter of FY23 and will be completed in FY25.
anchor

Justification

This project will complement the investment in US 29 Flash and improve transit travel time, reliability, performance, and person throughput from MD 198 to the Silver Spring Transit Center. These efforts will support master plan non-auto-driver mode share (NADMS) goals. The project supports the following Countywide vision goals: Easier Commutes and a Growing Economy. Approved land use plans in the corridor recommend the implementation of transit lanes along with US 29 Flash. The project is consistent with the Countywide Transit Corridors Functional Master Plan.
anchor

Fiscal Note

State aid reflects State grants for capital projects in Montgomery County programmed or preauthorized during the 2022 Maryland General Assembly Session. FY24 State Aid of $3,500,000 was preauthorized in 2022. FY23 supplemental in Impact Tax for the amount of $4,500,000 and State aid for the amount of $5,000,000 to advance the project to preliminary engineering.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park and Planning Commission
Download & Explore
Budget Snapshot
$9.75M Total
Expenditures/Funding
$3.49M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502201
Date Last Modified01/07/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision9744283597034913491000000
Land00000000000
Site Improvements and Utilities00000000000
Construction66000000000
Other00000000000
Total Expenditures9750289597034913491000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Impact Tax4750289446100000000
State Aid50000150934913491000000
Total Funding Sources9750289597034913491000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY22
Appropriation FY 26 Request0
Last FY's Cost Estimate9750
Cumulative Appropriation9750
Expenditure / Encumbrances1055
Unencumbered Balance8695