Description

This project provides for the replacement of the existing Garrett Park Road Bridge over Rock Creek. The existing bridge, built in 1965, is a three span (39'-75.5'-34') steel beam with concrete deck structure carrying a 24'-0" clear roadway with a 5'-0" sidewalk. The proposed replacement includes the removal and replacement of the concrete piers, abutments, and the replacement of the superstructure with prestressed Northeast Extreme Tee Beam (NEXT) beams. The proposed work includes new street lighting along Garrett Park Road, new approach slabs, and less than 100' of approach roadway work at each end of the bridge with modifications made to the intersection with Beach Drive. The road and bridge will be completely closed to vehicular traffic during construction and a temporary pedestrian bridge will be constructed over Rock Creek to maintain the high volume of pedestrian/bicycle traffic that use the bridge.
project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$10.51M Total
Expenditures/Funding
$6.73M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 9,400 vehicles and the roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

The design of the project was completed in the fall of 2025. Construction is scheduled to start in summer of 2026 and be completed in fall 2026. The bridge will be closed to traffic during the summer of 2026.
anchor

Cost Change

Cost increases due to construction costs inflation and WSSC waterline relocation.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition. The 2024 Bridge Inspection Report indicates that the bridge concrete piers are in serious condition with large areas of cracked, spalled, and delaminated concrete. The bridge is considered structurally deficient and functionally obsolete. The bridge is currently posted for a 10,000 lb. limit for a single-unit truck and a 10,000 lb. limit for a combination-unit truck. School buses and Ride On buses exceed the load posting, however, the Montgomery County Department of Transportation (MCDOT) granted a waiver for school buses to cross the bridge. For safety reasons, MCDOT increased the frequency of inspection to three months instead of the Federal requirement of 24 months.
anchor

Fiscal Note

The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal Aid. The design costs for this project are covered in the Bridge Design project (No. 509132). Intergovernmental funding represents WSSC Water line relocation.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement and Rehabilitation Program , Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, and Bridge Design Project (CIP 509132)
Download & Explore Project Details
Budget Snapshot
$10.51M Total
Expenditures/Funding
$6.73M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP502105
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision84212347483483000000
Land6206200000000
Site Improvements and Utilities00000000000
Construction96030335662476247000000
Other00000000000
Total Expenditures1050712376567306730000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid785812181660306030000000
G.O. Bonds19490194900000000
Intergovernmental70000700700000000
Total Funding Sources1050712376567306730000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request2101
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate8406
Cumulative Appropriation8406
Expenditure / Encumbrances12
Unencumbered Balance8394