Description

This project provides for the design and construction of the Fenton Street Cycletrack in the Silver Spring Central Business District (CBD) Bicycle and Pedestrian Priority Area (BiPPA). Recommended improvements include the construction of a separated bikeway between King Street and Planning Place along Fenton Street and will include wayfinding, stormwater management, ADA improvements, and other treatments intended to improve safety and mobility for people walking and biking.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$17.5M Total
Expenditures/Funding
$12.22M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design is underway and is expected to be complete in FY26. Utility relocation is expected to begin in FY26. Construction is anticipated to begin in FY27 and be completed in FY28.
anchor

Cost Change

Cost change due to inflation and utility relocations.
anchor

Justification

This project will create a low-stress bicycle route along Fenton Street from King Street to Planning Place, connecting the future purple line station with businesses, restaurants, and residential development along Fenton Street. The Bicycle Master Plan calls for separated bike lanes which will provide a high-quality low-stress route connection to the Green Trail, Wayne Ave / Second Avenue, and Spring Street / Cedar Street separated bikeway. Pedestrian safety treatments are also included in the project. These efforts will also meet master-planned non-auto-driver mode share (NADMS) goals. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County roadways to zero by 2030. Additional elements have been added to the project to improve accessibility for people with disabilities. Stormwater management best practices will be incorporated to the maximum extent practical.
anchor

Fiscal Note

FY25 actuals funding switch between GO bonds and Impact Taxes.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Department of Permitting Services, Maryland-National Capital Park and Planning Commission, Maryland DOT State Highway Administration, Silver Spring Regional Services Center, Silver Spring Urban District, utility companies, Washington Metropolitan Area Transit Authority
Download & Explore Project Details
Budget Snapshot
$17.5M Total
Expenditures/Funding
$12.22M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP502001
Date Last Modified01/11/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision5190245915811150100015000000
Land42022919100000000
Site Improvements and Utilities450045000000000
Construction114383670110719642142900000
Other00000000000
Total Expenditures17498305522221222110642157900000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds1531086722221222110642157900000
Impact Tax21882188000000000
Total Funding Sources17498305522221222110642157900000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32
Maintenance25-55555
NET IMPACT25-55555
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request1331
Year First AppropriationFY20
Appropriation FY 28 Request0
Last FY's Cost Estimate16167
Cumulative Appropriation16167
Expenditure / Encumbrances3383
Unencumbered Balance12784