up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Beach Drive Bridge over Silver Creek. The existing bridge, built in 1964, consists of three steel plate arches. The bridge provides a 24'-0" wide clear roadway with a 7'-0" Rock Creek Trail on the north side and has two 1'-9" parapets. The proposed replacement bridge includes a single span prestressed concrete slab beam structure carrying a 22'-0" roadway and a 5'-4" shoulder on each side. This width will allow for the implementation of safe on-road bicycling in accordance with the Master Plan. The Rock Creek Trail will be relocated to cross Silver Creek approximately 90 feet north of the proposed Beach Drive Bridge. This will improve safety by separating the pedestrian and light-use bicycle traffic from the vehicular traffic. The project includes approach roadway work at each end of the bridge as necessary to tie in to the existing roadway. The bridge and road will be closed to traffic during construction. In order to maintain pedestrian traffic on Rock Creek Trail during construction, the pedestrian bridge, and its approaches will be constructed prior to the removal of the existing Beach Drive Bridge. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
project image
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$4.2M Total
Expenditures/Funding
$4.2M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 5,500 and the roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

The design of the project is expected to finish in the winter of 2018. Construction is scheduled to start in spring 2020 and be completed in fall of 2020. Bridge will be closed to traffic from June 2020 to August 2020. This is a summer only construction project.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the travelling public. The 2015 bridge inspection revealed that the steel arches are in poor condition. There is laminar corrosion on the arches above and below the waterline up to 3'-0" high above the footing. Arch 1 and Arch 3 have holes in the steel along the west side. Arch 2 has heavy corrosion with moderate to severe section loss at the waterline and at isolated locations on the arch walls. The holes in the arches can be probed up to 6" deep. The south parapet has been removed above Arches 2 and 3, as well as along the Southeast Wingwall. Temporary concrete traffic barrier sections have been placed along the south side of the bridge. The north spandrel wall has isolated areas of minor deterioration of the mortar joints. There is moderate efflorescence and corrosion staining between the north spandrel wall and the arches. The south spandrel wall is separated up to 3 inches from the edge of Arch 1. There is a concrete fascia repair from Arch 2 to the east side of Arch 3. Implementation of this project would allow the bridge to be restored to full capacity. The 1989 Kensington-Wheaton Master Plan designates Beach Drive as Park Road. The 2005 Countywide Bikeways Functional Master Plan calls for signed shared roadway (SR-16)
anchor

Other

Project design costs are covered in the "Bridge Design" project (No. 509132).
anchor

Fiscal Note

The costs of bridge construction and construction management for this project are eligible for up to 80 percent Federal Aid.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement/Rehabilitation Program, Maryland State Highway Administration, Maryland Department of the Environment, Maryland National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, Bridge Design Project CIP (No. 509132).
Budget Snapshot
$4.2M Total
Expenditures/Funding
$4.2M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501903
Date Last Modified02/13/18
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
Planning, Design and Supervision3750037501901850000
Land50050500000
Site Improvements and Utilities00000000000
Construction38220038220159722250000
Other00000000000
Total Expenditures42020042020179224100000
FUNDING (000s)
Funding SourceTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
Federal Aid2790002790090618840000
G.O. Bonds141200141208865260000
Total Funding Sources42020042020179224100000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 19 Request0
Year First Appropriation
Appropriation FY 20 Request4202
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0