up
Budget Year / Version:  
anchor
anchor
anchor

Description

The project is for the comprehensive renovation and expansion of the Theatre Arts Building at the Rockville Campus to address current facility problems and programmatic needs. The entire building (21,967 NASF/35,032 GSF) will be renovated, and a building addition of 8,800 NASF /22,480 GSF is planned. It will include the complete interior renovation and reconfiguration of each floor, including modernization and upgrades to building systems and equipment serving these floors. The purpose of the TA Building Renovation/Addition is two-fold. It has been developed to support and advance the mission and strategic initiatives of the College and be in alignment with the recommendations of the most recent campus facilities master plan, updated in February of 2022. In addition, this project is intended to address the specific facilities needs to support the Theatre Arts curriculum and program.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$83.2M Total
Expenditures/Funding
$8.35M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

The design will be completed over a two-year period beginning in FY26.
anchor

Cost Change

State allowable cost escalation of 5 percent included.
anchor

Justification

The Theatre Arts Building is a 35,032 GSF two-story structure, including a small basement space, constructed in 1966 and renovated in 1995, it houses a theatrical performance auditorium, as well as supporting offices, classrooms, laboratories and other performance-support spaces. The entry sequence into the building is confusing, while the internal circulation is inefficient and disruptive. The building envelope does not meet current performance standards, while finishes and systems inside the building have generally outlived their useful lives. The Rockville Campus has a space surplus of 91,228 NASF, & a 2032 projected space deficit of 250,649 NASF. Relevant studies include the Montgomery College Strategic Plan (7/28), and Collegewide Facilities Master Plan (Pending 2023).
anchor

Other

This project, 662502, replaces project 662401, which was submitted by the College. Funding will be split 50/50 between the County and the State of Maryland.

anchor

Fiscal Note

Source of FY26 Contributions is College Fund Balance.
anchor

Disclosures

Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Roof Replacements Project
Download & Explore
Budget Snapshot
$83.2M Total
Expenditures/Funding
$8.35M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP662502
Date Last Modified05/20/24
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision83500083500835000000
Land00000000000
Site Improvements and Utilities00000000000
Construction6423600000000064236
Other1061200000000010612
Total Expenditures8319800835008350000074848
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Contributions41750041750417500000
G.O. Bonds3742400000000037424
State Aid4159900417504175000037424
Total Funding Sources8319800835008350000074848
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First Appropriation
Appropriation FY 26 Request8350
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0