Description

This project provides funding for the design and construction of a new academic building (108,000 gross square feet) supporting science programs, such as biology, chemistry, computer science and cybersecurity, engineering, geology, physics, and the mathematics department, as described in the Collegewide Facilities Master Plan, 2013-2023 (2/16). The new math and science building will replace the Science South and Falcon Hall buildings, which will be demolished, and the new building will be constructed on this site. During FY18, the building was renamed to the Catherine and Isiah Leggett Math and Science Building.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$102.9M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Construction started in November 2019 and is expected to conclude in Spring 2024.
anchor

Cost Change

A fund transfer was made to this project, as noted under the "Other" section.
anchor

Justification

Under the application of the State space guidelines, the enrollment growth on the Takoma Park/Silver Spring Campus has resulted in a significant instructional space deficit. The Takoma Park/Silver Spring Campus has a Fall 2018 laboratory space deficit of 67,128 NASF and a total space deficit of 731 NASF. The 2028 projected laboratory space deficit is 60,069 NASF and the total space deficit is anticipated to be 74,034 NASF. The construction of the math & science building will address this deficit as well as replace Science South and Falcon Hall, which are in exceedingly poor condition (as identified in the Collegewide Facilities Condition Assessment, 12/13). Relevant studies include the Montgomery College Strategic Plan, Collegewide Facilities Condition Assessment (1/23), and the Collegewide Facilities Master Plan (Pending 2023).
anchor

Other

Funding sources: GO Bonds, and State Aid. Relocation costs and design fees above approximately 7% of estimated construction costs may not be eligible for State reimbursement.
In FY22 as part of the County Council FY23 Capital Budget approval, funds of $2,900,000 were transferred from the Rockville Student Services Center project (P076604). The additional funds are needed to support increased escalation costs. A fund transfer was made to this project $1,000,000 from Planning, Design, and Construction(#P906605), and $2,100,000 from Capital Renewal(#P096600) (BOT Resol. #23-06-093, and #23-06-094, 06/21/23).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Facility Planning: College (CIP No. P886686)
Budget Snapshot
$102.9M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP076607
Date Last Modified01/05/24
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision10276990637000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction8192676106582000000000
Other107004404629242200000
Total Expenditures102902904161248242200000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds5300145208779121100000
State Aid4990145208469121100000
Total Funding Sources102902904161248242200000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY16
Appropriation FY 26 Request0
Last FY's Cost Estimate99802
Cumulative Appropriation102902
Expenditure / Encumbrances90416
Unencumbered Balance12486