up
Budget Year / Version:  
anchor
anchor
anchor

Description

Projections indicate that student enrollment at Burtonsville Elementary School will exceed capacity by the end of the six-year planning period. An FY 2023 appropriation was requested for planning funds to begin this project. Due to fiscal constraints, the County Council delayed the completion date for this project by two years, but maintained a portion of the planning funds. As part of the adopted FY2023-2028 CIP, an additional $3.0 million from the county executive's Prevailing Wage and Built to Learn Act PDFs was included in this project to maximize state aid. An FY 2024 appropriation and an amendment to the FY2023-2028 CIP was approved to construct a new Burtonsville ES at another location instead of building an addition at the existing school at the current location. An FY 2025 appropriation was approved for construction cost increases and for the balance of funding for this project. As a result of the relocation of Burtonsville ES, the completion date was accelerated one year, therefore, the scheduled completion date is August 2026.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$59.06M Total
Expenditures/Funding
$17.54M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the Built To Learn Act for school construction program. FY25 supplemental in State Aid for the amount of $1,285,000 from the Decarbonizing Public Schools Program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore Project Details
Budget Snapshot
$59.06M Total
Expenditures/Funding
$17.54M 6 Year Total
Expenditures/Funding
anchor
Project NumberP652301
Date Last Modified11/24/25
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaFairland-Beltsville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision3098269740100000000
Land00000000000
Site Improvements and Utilities52602709255100000000
Construction493781159306831753617536000000
Other13250132500000000
Total Expenditures590616565349601753617536000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds19780118718647-54-54000000
Recordation Tax15171517000000000
Schools Impact Tax38613861000000000
State Aid339030163131759017590000000
Total Funding Sources590616565349601753617536000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY23
Appropriation FY 28 Request0
Last FY's Cost Estimate59061
Cumulative Appropriation59061
Expenditure / Encumbrances0
Unencumbered Balance59061
anchor
Download & Explore Project Details