up
Budget Year / Version:  
anchor
anchor
anchor

Description

Projections indicate that enrollment will exceed capacity through the six-year planning period. In addition, based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. An FY 2021 appropriation was requested for the architectural planning and design for this project. Due to fiscal constraints, the County Council, in the adopted FY2021-2026 CIP, approved the completion date one year beyond the Board of Education's request, but approved the appropriation for planning funds. This Major Capital Project is scheduled to be completed January 2025. An FY 2022 appropriation and amendment to the FY 2021-2026 CIP was approved to accelerate this project 18 months, six-months ahead of the Board of Education's request in the FY 2021-2026 CIP. The acceleration of the additional six-months is possible due to the utilization of the former Carl Sandburg Learning Center as a holding facility. An FY 2022 supplemental appropriation and transfer of funds of $4.840 million for this project was approved, in September 2021, to address increases in construction costs. An FY 2022 supplemental appropriation of $3.528 million was approved, in December 2021, to maximize state aid for this project. An FY 2023 appropriation was approved to complete this project. The scheduled completion date is August 2023.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$43.23M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid approved from the County's allocation of the Built To Learn Act school construction program. FY24 transfer in for $1,000,000 in GO Bonds from Ashburton ES Add (P651514), Clarksburg Cluster ES (P651713), Dufief ES/Add Facility Upgrade (P651903), Noth Bethesda MS Add (P651503), and Current Rev/Ex (P926575).

anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$43.23M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP652111
Date Last Modified12/19/25
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCloverly-Norwood
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision20522052000000000
Land00000000000
Site Improvements and Utilities37623762000000000
Construction356243523838600000000
Other17961796000000000
Total Expenditures432344284838600000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds175941720838600000000
Recordation Tax78787878000000000
State Aid1776217762000000000
Total Funding Sources432344284838600000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY21
Appropriation FY 28 Request0
Last FY's Cost Estimate43794
Cumulative Appropriation43234
Expenditure / Encumbrances0
Unencumbered Balance43234