Budget Year / Version:  
anchor
anchor
anchor

Description

This level of effort project is intended to provide a structured process to ensure that all recreation indoor pool facilities are refurbished through repair or replacement of facility components. A facility assessment will be conducted to evaluate the level of repair or replacement for each facility and create a program of requirements with an associated construction cost estimate.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$16.9M Total
Expenditures/Funding
$16.9M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

The Department of Recreation will identify the facilities and scope of the work through a facility assessment prior to the design and construction process. Projects will be prioritized based on facility assessment results and programmatic needs.
anchor

Justification

Some of the Department of Recreation's indoor pool facilities have not been updated for a long time. This project will ensure that: 1) the County's capital investments are protected by maintaining the Department's infrastructure, 2) all new and required construction codes are addressed and implemented, 3) critical equipment and building systems are overhauled or replaced prior to failure, and 4) reorganization of internal space is completed to ensure that space is fully utilized based on the community's needs for programs and services.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Department of General Services and Department of Recreation.
Budget Snapshot
$16.9M Total
Expenditures/Funding
$16.9M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP722506
Date Last Modified04/17/24
Administering AgencyRecreation
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision35600035606731580979210834940
Land00000000000
Site Improvements and Utilities00000000000
Construction1306700130671067023333667383321670
Other27800278670355573480
Total Expenditures169050016905120131531774514498927090
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds169050016905120131531774514498927090
Total Funding Sources169050016905120131531774514498927090
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1201
Year First Appropriation
Appropriation FY 26 Request315
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0