Description

This project supports the development of a Comprehensive Flood Management Plan (CFMP) for Montgomery County.

The CFPM will improve the County's ability to address flooding based on scientific and engineering data and use a comprehensive, coordinated approach to identify potentially affected residents and businesses, particularly underserved communities and businesses that are least prepared to respond to and recover from flooding events. The CFPM will, among other things:

  • gather data on historic flooding in the County, including input from affected communities;
  • examine the potential impacts of climate change and other significant factors that can cause flooding in the County, including the effect of updated rainfall predictions;
  • provide recommendations for regulatory, policy, and organizational changes necessary for the County to comprehensively plan for, respond to, and recover from flooding events; and
  • include detailed hydrologic and hydraulic modeling, vulnerability assessments, and the development of adaptation/mitigation design plans.
Typical tasks in the development of specific watershed/sub-watershed assessments may include evaluations of current risk, future risk due to climate change, and assessment of risk due to aging assets. More specifically, the effort will include identifying areas at risk of flooding, quantifying that risk, developing mitigation alternatives, and conducting cost-benefit analyses, including evaluation of impacts to disadvantaged communities. Additional results will include development of prioritized capital improvement program projects and implementation schedules. The level of detail and budget required to accomplish these tasks will vary by watershed. There are 8 major watersheds and almost 150 smaller watersheds in the County.

This study will complement the State's efforts under Stormwater Management Law, Environment Article 4-201.1, which requires the Maryland Department of the Environment (MDE) to report on the most recent precipitation data available, investigate flooding events since 2000, and update Maryland's stormwater quantity management standards for flood control.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$7.24M Total
Expenditures/Funding
$4.64M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Phase 1 will identify watersheds for detailed modeling in Phase 2 and provide an assessment of current County programs, policies, budgets, and other components of the County's flood management activities. Phase I was completed in May 2023. Modeling of specific watersheds and continued analysis of the County's flood-related programs, policies, etc. began in FY24.
anchor

Cost Change

Costs increase so that all planned watersheds can be analyzed.
anchor

Justification

Flooding incidents in Montgomery County have been increasing in frequency and severity for several years. The built environment also affects flooding. An April 2021 report from the Office of Legislative Oversight (OLO) identified an upward trend of urban flooding in the County, from two to four occurrences a year before 2010 to 11 to 39 occurrences per-year since 2010; and that the severity has increased in terms of property damage and loss of life. According to the U.S. Environmental Protection Agency, precipitation in Maryland has increased by about 5 percent in the last century but precipitation from extremely heavy storms has increased in the eastern United States by more than 25 percent since 1958.

To determine the best way to address flooding problems, the County needs a systematic watershed and sub-watershed-based analysis of flooding, a better understanding of the impact the County will experience from increased rainfall linked to climate change, and other significant contributing factors.

anchor

Fiscal Note

In addition to County support, the Department of Environmental Protection will pursue outside funding to fund these efforts. An FY22 supplemental added Current Revenue: General for the amount of $1,300,000. FY25 includes a funding switch to reduce Intergovernmental and increase Current Revenue: WQP, including $75,000 from prior appropriation. In FY26, $1,500,000 is shifted from the Implementation of the Comprehensive Flood Management Plan project.
anchor

Coordination

Department of Permitting Services, Office of Emergency Management and Homeland Security, Department of Transportation, Montgomery County Fire and Rescue Service, Maryland-National Capital Park and Planning Commission, Maryland Department of the Environment, U.S. Army Corps of Engineers
Budget Snapshot
$7.24M Total
Expenditures/Funding
$4.64M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP802202
Date Last Modified01/07/25
Administering AgencyEnvironmental Protection
CategoryConservation of Natural Resources
SubCategoryStormwater Management
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision62308167794635273315004020000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other101146554600000000
Total Expenditures7241128113254635273315004020000
FUNDING (000s)
Funding SourceTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Current Revenue: General130046583500000000
Current Revenue: Water Quality Protection58168163654635273315004020000
Intergovernmental125012500000000
Total Funding Sources7241128113254635273315004020000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request2139
Year First AppropriationFY22
Appropriation FY 26 Request1500
Last FY's Cost Estimate5339
Cumulative Appropriation5339
Expenditure / Encumbrances2497
Unencumbered Balance2842